2531 E GLEASON AVE 90033
Certificate Information: 2531 E GLEASON AVE 90033
- Application / Permit
- 22010-10000-00240
- Plan Check / Job No.
- B22LA00718
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 2-STORY SINGLE FAMILY DWELLING. FULLY SPRINKLERED NFPA-13D
- Permit Issued
- Issued on 5/10/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2022 | AUNG SOE |
| Corrections Issued | 2/1/2022 | AUNG SOE |
| Quality Review Completed | 2/1/2022 | EUGENE BARBEAU |
| Building Plans Picked Up | 2/15/2022 | APPLICANT |
| Applicant returned to address corrections | 4/28/2022 | AUNG SOE |
| Plan Check Approved | 5/10/2022 | AUNG SOE |
| Issued | 5/10/2022 | APPLICANT |
| CofO in Progress | 1/31/2023 | FREDDIE RIVERA |
| Permit Finaled | 2/7/2023 | DEROLD HAUFF |
| CofO Issued | 2/7/2023 | DEROLD HAUFF |
| Permit Finaled | 2/7/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/30/2022 | AUNG SOE |
| Address approval | Cleared | 2/1/2022 | CELINA MORENO |
| Permit | Cleared | 2/1/2022 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 2/2/2022 | CELINA MORENO |
| Sewer availability | Cleared | 2/2/2022 | CELINA MORENO |
| Tenant Habitability Plan | Cleared | 2/2/2022 | ISMAEL HERNANDEZ |
| Clean Up Green Up | Cleared | 2/28/2022 | RICHARD REASER |
| ZA Case | Cleared | 2/28/2022 | RICHARD REASER |
| ZA Case | Cleared | 2/28/2022 | RICHARD REASER |
| Hydrant and Access approval | Cleared | 3/11/2022 | CINDY JOSSELYN |
| Frnt yard landscape/Water mgmt | Cleared | 4/6/2022 | RICHARD REASER |
| Redevelopment Project Area | Cleared | 4/7/2022 | SUSAN WONG |
| Low Impact Development | Cleared | 4/18/2022 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 4/20/2022 | CELINA MORENO |
Contact Information
| Contractor | Martinez David; Lic. No.: 1013460-B | 2843 S HOLT AVENUE LOS ANGELES, CA 90034 |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
| Engineer | Wang,, Kenneth Kaiyen; Lic. No.: C25386 | 147 PALATINE DR ALHAMBRA, CA 91801 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/27/2022 | Approved | RUBEN SALAS |
| Underground Mechanical | 8/3/2022 | Partial Approval | RUBEN SALAS |
| Wood Frame | 8/3/2022 | Partial Approval | RUBEN SALAS |
| Insulation | 8/4/2022 | Partial Approval | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2022 | Partial Approval | FREDDIE RIVERA |
| Wood Frame | 9/1/2022 | Partial Inspection | FREDDIE RIVERA |
| Deputy Wood Construction | 9/23/2022 | Conditional Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2022 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 10/20/2022 | Partial Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2022 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 10/20/2022 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 10/20/2022 | Partial Inspection | FREDDIE RIVERA |
| Wood Frame | 10/20/2022 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 10/24/2022 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 10/24/2022 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 10/24/2022 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 10/25/2022 | Partial Inspection | FREDDIE RIVERA |
| Green Building Rough | 10/25/2022 | Partial Inspection | FREDDIE RIVERA |
| Interior/Exterior Lathing | 10/25/2022 | Partial Approval | FREDDIE RIVERA |
| METHANE-Rough | 10/25/2022 | Partial Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 10/25/2022 | Partial Inspection | FREDDIE RIVERA |
| Wood Frame | 10/25/2022 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 11/1/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Rough | 11/1/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| METHANE-Rough | 11/1/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 11/1/2022 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 11/1/2022 | Approved | ALIZAH MAYAGOITIA |
| Wood Frame | 11/1/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 11/3/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Rough | 11/3/2022 | Approved | ALIZAH MAYAGOITIA |
| METHANE-Rough | 11/3/2022 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 11/9/2022 | Approved | FREDDIE RIVERA |
| Shower Pan | 11/9/2022 | Corrections Issued | FREDDIE RIVERA |
| Drywall Nailing | 11/17/2022 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 11/17/2022 | Approved | FREDDIE RIVERA |
| Shower Pan | 11/17/2022 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 12/22/2022 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Final | 12/22/2022 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Final | 12/29/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 12/29/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 1/13/2023 | Approved | FREDDIE RIVERA |
| Final | 1/13/2023 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 1/13/2023 | Approved | FREDDIE RIVERA |
| Green Building Final | 1/13/2023 | Corrections Issued | FREDDIE RIVERA |
| METHANE-Barrier | 1/13/2023 | Approved | FREDDIE RIVERA |
| METHANE-Subgrade | 1/13/2023 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 1/13/2023 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 1/13/2023 | Approved | FREDDIE RIVERA |
| Smoke Detectors | 1/13/2023 | Approved | FREDDIE RIVERA |
| Final | 1/19/2023 | Partial Inspection | FREDDIE RIVERA |
| Green Building Final | 1/19/2023 | Approved | FREDDIE RIVERA |
| Final | 1/31/2023 | OK to Issue CofO | FREDDIE RIVERA |