218 1/2 S DETROIT ST 90036

Certificate Information: 218 1/2 S DETROIT ST 90036

Application / Permit
22010-10000-00221
Plan Check / Job No.
B22LA00665
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan 2-story ADU addition. PROPOSED 2ND STORY ADU ADDITION OVER EXISTING DETACHED GARAGE
Permit Issued
Issued on 3/22/2023
Issuing Office
Current Status
CofO Issued on 9/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/18/2022 APPLICANT
Assigned to Plan Check Engineer 4/14/2022 CRYSTEL MAALOUF
Corrections Issued 4/26/2022 CRYSTEL MAALOUF
Quality Review Completed 5/23/2022 FARUK SEZER
Applicant returned to address corrections 7/27/2022 CRYSTEL MAALOUF
Applicant returned to address corrections 11/17/2022 CRYSTEL MAALOUF
Applicant returned to address corrections 12/13/2022 CRYSTEL MAALOUF
Applicant returned to address corrections 1/10/2023 CRYSTEL MAALOUF
Plan Check Approved 1/23/2023 CRYSTEL MAALOUF
Issued 3/22/2023 APPLICANT
CofO in Progress 9/9/2024 EDWIN GREGORYONA
CofO Issued 9/9/2024 ERNESTO CORRAL
Permit Finaled 9/9/2024 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 5/27/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 6/7/2022 AMAAN MALIK
Sewer availability Cleared 6/7/2022 AMAAN MALIK
CPC Cleared 10/27/2022 DAMIAN GATTO
CPC Cleared 10/27/2022 DAMIAN GATTO
HPOZ Cleared 10/27/2022 DAMIAN GATTO

Contact Information

Contractor Retrofitting360 Inc; Lic. No.: 1039226-B       ,
Engineer Durand,, Paul H; Lic. No.: S4222 611 N G ST      OXNARD, CA 93030

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/2/2023 Not Ready for Inspection ALFREDO LOPEZ
METHANE-Barrier 6/2/2023 Not Ready for Inspection ALFREDO LOPEZ
METHANE-Subgrade 6/2/2023 Not Ready for Inspection ALFREDO LOPEZ
Deputy Reinf. Concrete 6/5/2023 Partial Approval JEROME BLACKWOOD
Deputy Reinf. Concrete 6/7/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 6/22/2023 Partial Approval ALFREDO LOPEZ
METHANE-Barrier 6/22/2023 Partial Inspection ALFREDO LOPEZ
METHANE-Subgrade 6/22/2023 Partial Inspection ALFREDO LOPEZ
Floor/Roof Diaphrgm/Shear Wall 7/26/2023 Not Ready for Inspection ALFREDO LOPEZ
Floor/Roof Diaphrgm/Shear Wall 8/1/2023 Partial Approval ALFREDO LOPEZ
Green Building Rough 8/1/2023 Not Ready for Inspection ALFREDO LOPEZ
METHANE-Rough 8/1/2023 Approved ALFREDO LOPEZ
Wood Frame 8/1/2023 Partial Approval ALFREDO LOPEZ
Final 8/31/2023 Not Ready for Inspection JEROME BLACKWOOD
Footing/Foundation/Slab 8/31/2023 Not Ready for Inspection JEROME BLACKWOOD
Green Building Final 8/31/2023 Not Ready for Inspection JEROME BLACKWOOD
Green Building Rough 8/31/2023 Not Ready for Inspection JEROME BLACKWOOD
METHANE-Barrier 8/31/2023 Not Ready for Inspection JEROME BLACKWOOD
METHANE-Subgrade 8/31/2023 Not Ready for Inspection JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 8/31/2023 SGSOV Not Ready JEROME BLACKWOOD
Smoke Detectors 8/31/2023 Not Ready for Inspection JEROME BLACKWOOD
Wood Frame 8/31/2023 Not Ready for Inspection JEROME BLACKWOOD
Green Building Rough 9/13/2023 Approved GREGORY POMISH
Wood Frame 9/13/2023 Approved GREGORY POMISH
Insulation 9/22/2023 No Access for Inspection ALAN MORELOS
Interior/Exterior Lathing 9/22/2023 No Access for Inspection ALAN MORELOS
Insulation 9/28/2023 Partial Approval JEROME BLACKWOOD
Interior/Exterior Lathing 9/28/2023 Not Ready for Inspection JEROME BLACKWOOD
Drywall Nailing 10/4/2023 Not Ready for Inspection JEROME BLACKWOOD
Interior/Exterior Lathing 10/4/2023 Not Ready for Inspection JEROME BLACKWOOD
Drywall Nailing 10/10/2023 Approved ALFREDO LOPEZ
Interior/Exterior Lathing 10/10/2023 Approved ALFREDO LOPEZ
Interior/Exterior Lathing 10/13/2023 Partial Approval JEROME BLACKWOOD
Final 7/18/2024 Not Ready for Inspection JACOB MYERS
Footing/Foundation/Slab 7/18/2024 Not Ready for Inspection JACOB MYERS
Green Building Final 7/18/2024 Approved JACOB MYERS
METHANE-Barrier 7/18/2024 Approved JACOB MYERS
METHANE-Subgrade 7/18/2024 Approved JACOB MYERS
SGSOV-Seismic Gas S/O Valve 7/18/2024 SGSOV Not Ready JACOB MYERS
Smoke Detectors 7/18/2024 Approved JACOB MYERS
Final 9/9/2024 OK to Issue CofO EDWIN GREGORYONA
Footing/Foundation/Slab 9/9/2024 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 9/9/2024 SGSOV Approved EDWIN GREGORYONA