4331 N ALLOTT AVE 91423
Certificate Information: 4331 N ALLOTT AVE 91423
- Application / Permit
- 22010-10000-00209
- Plan Check / Job No.
- B21LA22340
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 796 SQ FT DETEACHED 3-CAR GARAGE AND NEW 796 SQ FT ADU ON TOP
- Permit Issued
- Issued on 5/23/2022
- Issuing Office
- Current Status
- CofO Issued on 4/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2021 | JAD BASMA |
| Corrections Issued | 1/12/2022 | JAD BASMA |
| Quality Review Completed | 1/25/2022 | MICHAEL PEREZ |
| Building Plans Picked Up | 2/18/2022 | APPLICANT |
| Plan Check Approved | 5/17/2022 | JAD BASMA |
| Issued | 5/23/2022 | APPLICANT |
| CofO in Progress | 1/23/2024 | MISAEL ESPARZA |
| Permit Finaled | 4/23/2024 | RUBEN SALAS |
| CofO Issued | 4/23/2024 | RUBEN SALAS |
| Permit Finaled | 4/23/2024 | RUBEN SALAS |
Permit Application Clearance Information
| ZI | Cleared | 3/1/2022 | MAYELA VILLA |
| Address approval | Cleared | 3/15/2022 | JOHN LIN |
| Address approval | Cleared | 3/15/2022 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 3/17/2022 | JOHN LIN |
| Sewer availability | Cleared | 3/17/2022 | JOHN LIN |
| Hydrant and Access approval | Cleared | 4/21/2022 | LAURINDA MEADE |
| Low Impact Development | Cleared | 5/13/2022 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 5/13/2022 | JOHN LIN |
Contact Information
| Contractor | 1st Choice Solar Construction; Lic. No.: 576474-B | 2400 E KATELLA AVENUE #800 ANAHEIM, CA 92806 |
| Engineer | Pontex, Engineering; Lic. No.: C70784 | 402 ENCLAVE COSTA MESA, CA 92626 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/3/2022 | Partial Approval | CALEB MEISTER |
| Excavation/Setback/Form/Re-Bar | 6/15/2022 | Corrections Issued | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 7/5/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 7/5/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 7/12/2022 | Corrections Issued | MISAEL ESPARZA |
| Pre-Inspection | 7/22/2022 | Approved | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 7/26/2022 | Corrections Issued | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 8/4/2022 | Corrections Issued | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 8/5/2022 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2022 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/7/2022 | Approved | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 9/13/2022 | Approved | MISAEL ESPARZA |
| Pre-Inspection | 11/7/2022 | Approved | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 1/19/2023 | Conditional Approval | ROBERT GOLD |
| Rough-Elec/Plmb/HVAC | 2/16/2023 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/22/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 2/22/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Rough-Elec/Plmb/HVAC | 2/22/2023 | Conditional Approval | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 2/22/2023 | Approved | MISAEL ESPARZA |
| Wood Frame | 2/22/2023 | Corrections Issued | MISAEL ESPARZA |
| Deputy Wood Construction | 3/15/2023 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 3/16/2023 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2023 | Partial Approval | MISAEL ESPARZA |
| Green Building Rough | 3/16/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 3/16/2023 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 3/16/2023 | Approved | MISAEL ESPARZA |
| Wood Frame | 3/16/2023 | Approved | MISAEL ESPARZA |
| Insulation | 3/30/2023 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 3/30/2023 | Partial Approval | MISAEL ESPARZA |
| Drywall Nailing | 4/18/2023 | Approved | MISAEL ESPARZA |
| Shower Pan | 4/18/2023 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 5/16/2023 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 12/13/2023 | Approved | MISAEL ESPARZA |
| Final | 12/13/2023 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 12/13/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 12/13/2023 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 12/13/2023 | SGSOV Not Ready | MISAEL ESPARZA |
| Service/Power Release | 12/13/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 12/13/2023 | Approved | MISAEL ESPARZA |
| Final | 1/12/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 1/12/2024 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 1/12/2024 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 1/12/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 1/19/2024 | OK to Issue CofO | MISAEL ESPARZA |
| Service/Power Release | 1/19/2024 | Approved | MISAEL ESPARZA |