NEW 796 SQ FT DETEACHED 3-CAR GARAGE AND NEW 796 SQ FT ADU ON TOP
Permit Issued
Issued on 5/23/2022
Issuing Office
Current Status
CofO Issued on 4/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/29/2021 APPLICANT
Assigned to Plan Check Engineer 12/29/2021 JAD BASMA
Corrections Issued 1/12/2022 JAD BASMA
Quality Review Completed 1/25/2022 MICHAEL PEREZ
Building Plans Picked Up 2/18/2022 APPLICANT
Plan Check Approved 5/17/2022 JAD BASMA
Issued 5/23/2022 APPLICANT
CofO in Progress 1/23/2024 MISAEL ESPARZA
Permit Finaled 4/23/2024 RUBEN SALAS
CofO Issued 4/23/2024 RUBEN SALAS
Permit Finaled 4/23/2024 RUBEN SALAS

Permit Application Clearance Information

ZI Cleared 3/1/2022 MAYELA VILLA
Address approval Cleared 3/15/2022 JOHN LIN
Address approval Cleared 3/15/2022 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 3/17/2022 JOHN LIN
Sewer availability Cleared 3/17/2022 JOHN LIN
Hydrant and Access approval Cleared 4/21/2022 LAURINDA MEADE
Low Impact Development Cleared 5/13/2022 KHAING AYE
Roof/Waste drainage to street Cleared 5/13/2022 JOHN LIN

Contact Information

Contractor 1st Choice Solar Construction; Lic. No.: 576474-B 2400 E KATELLA AVENUE #800      ANAHEIM, CA 92806
Engineer Pontex, Engineering; Lic. No.: C70784 402 ENCLAVE      COSTA MESA, CA 92626

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/3/2022 Partial Approval CALEB MEISTER
Excavation/Setback/Form/Re-Bar 6/15/2022 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 7/5/2022 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 7/5/2022 Not Ready for Inspection MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 7/12/2022 Corrections Issued MISAEL ESPARZA
Pre-Inspection 7/22/2022 Approved MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 7/26/2022 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 8/4/2022 Corrections Issued JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 8/5/2022 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 8/18/2022 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 8/23/2022 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 9/7/2022 Approved MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 9/13/2022 Approved MISAEL ESPARZA
Pre-Inspection 11/7/2022 Approved MISAEL ESPARZA
Deputy Drilled-In Anchors 1/19/2023 Conditional Approval ROBERT GOLD
Rough-Elec/Plmb/HVAC 2/16/2023 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 2/22/2023 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 2/22/2023 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 2/22/2023 Not Ready for Inspection MISAEL ESPARZA
Rough-Elec/Plmb/HVAC 2/22/2023 Conditional Approval MISAEL ESPARZA
Verify Sprinkler Sign Off 2/22/2023 Approved MISAEL ESPARZA
Wood Frame 2/22/2023 Corrections Issued MISAEL ESPARZA
Deputy Wood Construction 3/15/2023 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 3/16/2023 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 3/16/2023 Partial Approval MISAEL ESPARZA
Green Building Rough 3/16/2023 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 3/16/2023 Approved MISAEL ESPARZA
PLUMBING-Rough 3/16/2023 Approved MISAEL ESPARZA
Wood Frame 3/16/2023 Approved MISAEL ESPARZA
Insulation 3/30/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 3/30/2023 Partial Approval MISAEL ESPARZA
Drywall Nailing 4/18/2023 Approved MISAEL ESPARZA
Shower Pan 4/18/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 5/16/2023 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 12/13/2023 Approved MISAEL ESPARZA
Final 12/13/2023 Corrections Issued MISAEL ESPARZA
Green Building Final 12/13/2023 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 12/13/2023 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 12/13/2023 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 12/13/2023 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 12/13/2023 Approved MISAEL ESPARZA
Final 1/12/2024 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 1/12/2024 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 1/12/2024 SGSOV Approved MISAEL ESPARZA
Service/Power Release 1/12/2024 Not Ready for Inspection MISAEL ESPARZA
Final 1/19/2024 OK to Issue CofO MISAEL ESPARZA
Service/Power Release 1/19/2024 Approved MISAEL ESPARZA