1037 W 78TH ST 90044

Certificate Information: 1037 W 78TH ST 90044

Application / Permit
22010-10000-00185
Plan Check / Job No.
B22LA00499
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* NEW DETACHED 1-STROY (42' X 16') ADU (605 SF) PER CA GC 65852.2(e)(1)(B) AND LAMC 12.22.A.33(c)-(d), (g).
Permit Issued
Issued on 9/27/2022
Issuing Office
Current Status
Issued on 9/27/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/19/2022 APPLICANT
Assigned to Plan Check Engineer 1/27/2022 VIVIAN LAO
Corrections Issued 1/29/2022 VIVIAN LAO
Quality Review Completed 1/31/2022 LIPING TENG
Applicant returned to address corrections 3/17/2022 VIVIAN LAO
Plan Check Approved 6/28/2022 VIVIAN LAO
Issued 9/27/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 2/23/2022 KHOUNG LE
Eng Process Fee Ord 176,300 Cleared 3/2/2022 KHOUNG LE
Sewer availability Cleared 3/2/2022 KHOUNG LE
Low Impact Development Cleared 5/25/2022 KHAING AYE
Roof/Waste drainage to street Cleared 6/16/2022 KHOUNG LE

Contact Information

Contractor L A Developing Inc; Lic. No.: 1083426-B 2926 CUDAHY STREET      HUNTINGTON PARK, CA 90255
Engineer Hwang,, Junho; Lic. No.: S5592 815 FAIRVIEW AVE #205      SOUTH PASADENA, CA 91030

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/4/2022 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 10/6/2022 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 10/14/2022 Approved LILIANA PORTILLO
Sewer 10/26/2022 Approved LILIANA PORTILLO
Underground Mechanical 10/26/2022 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 11/1/2022 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 11/21/2022 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 11/21/2022 Corrections Issued LILIANA PORTILLO
Deputy Wood Construction 11/22/2022 Conditional Approval LILIANA PORTILLO
BUILDING-Rough-Frame 11/29/2022 Conditional Approval LILIANA PORTILLO
ELECTRICAL-Rough 11/29/2022 Not Ready for Inspection LILIANA PORTILLO
HVAC-Rough 11/29/2022 Approved LILIANA PORTILLO
PLUMBING-Rough 11/29/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 12/2/2022 Approved LILIANA PORTILLO
ELECTRICAL-Rough 12/2/2022 Approved LILIANA PORTILLO
Green Building Rough 12/2/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 12/2/2022 Partial Approval LILIANA PORTILLO
Verify Sprinkler Sign Off 12/2/2022 Approved LILIANA PORTILLO
Insulation 12/7/2022 Corrections Issued LILIANA PORTILLO
Drywall Nailing 12/12/2022 Approved LILIANA PORTILLO
Insulation 12/12/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 12/29/2022 Not Ready for Inspection HORACE FULTZ
Interior/Exterior Lathing 12/30/2022 Partial Approval LILIANA PORTILLO
Interior/Exterior Lathing 1/3/2023 Approved LILIANA PORTILLO
ELECTRICAL-Final 1/23/2023 Corrections Issued LILIANA PORTILLO
PLUMBING-Final 2/2/2023 Corrections Issued LILIANA PORTILLO
Gas Test 2/14/2023 Approved LILIANA PORTILLO
PLUMBING-Final 2/14/2023 Approved LILIANA PORTILLO
ELECTRICAL-Final 2/21/2023 Corrections Issued LILIANA PORTILLO
HVAC-Final 2/21/2023 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 2/21/2023 SGSOV Approved LILIANA PORTILLO
Final 3/6/2023 Corrections Issued LILIANA PORTILLO
HVAC-Final 3/6/2023 Approved LILIANA PORTILLO
Final 6/22/2023 Corrections Issued STUART CHAPMAN
Green Building Final 6/22/2023 Approved STUART CHAPMAN
PLUMBING-Rough 6/22/2023 Not Ready for Inspection STUART CHAPMAN
Service/Power Release 6/22/2023 Approved STUART CHAPMAN
Smoke Detectors 6/22/2023 Approved STUART CHAPMAN