9115 S ORCHARD AVE 90044

Certificate Information: 9115 S ORCHARD AVE 90044

Application / Permit
22010-10000-00184
Plan Check / Job No.
B22LA00498
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan PROPOSED 1 STORY ADU PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 6/20/2022
Issuing Office
Current Status
Issued on 6/20/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/13/2022 APPLICANT
Assigned to Plan Check Engineer 2/10/2022 CRYSTEL MAALOUF
Corrections Issued 2/22/2022 CRYSTEL MAALOUF
Quality Review Completed 2/22/2022 HERNAN ARREOLA
Applicant returned to address corrections 4/7/2022 CRYSTEL MAALOUF
Plan Check Approved 5/13/2022 CRYSTEL MAALOUF
Issued 6/20/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/21/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 3/22/2022 WALLIE JONG
Sewer availability Cleared 3/22/2022 WALLIE JONG
Low Impact Development Cleared 5/6/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 5/6/2022 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,
Engineer Yiu,, Siu Fung; Lic. No.: S5801 PO BOX 5143      EL MONTE, CA 91734

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/27/2022 Partial Approval LILIANA PORTILLO
Footing/Foundation/Slab 8/4/2022 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 8/15/2022 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 9/28/2022 Corrections Issued LILIANA PORTILLO
Wood Frame 9/28/2022 Corrections Issued LILIANA PORTILLO
Deputy Wood Construction 9/30/2022 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/12/2022 Partial Approval LILIANA PORTILLO
ELECTRICAL-Rough 6/1/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 6/1/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 8/15/2023 Approved MICHAEL LEWIS
Green Building Rough 8/15/2023 Approved MICHAEL LEWIS
HVAC-Rough 8/15/2023 Approved MICHAEL LEWIS
Insulation 8/15/2023 Corrections Issued MICHAEL LEWIS
Verify Sprinkler Sign Off 8/15/2023 Approved MICHAEL LEWIS
Deputy Wood Construction 8/17/2023 Conditional Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 10/3/2023 Approved MICHAEL LEWIS
Insulation 10/3/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 10/3/2023 Approved MICHAEL LEWIS
Drywall Nailing 10/12/2023 Approved MICHAEL LEWIS
Shower Pan 10/12/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 10/20/2023 Approved MICHAEL LEWIS
Sewer 10/20/2023 Approved MICHAEL LEWIS
Underground Mechanical 10/20/2023 Approved MICHAEL LEWIS
Final 3/27/2024 Corrections Issued MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 3/27/2024 SGSOV Not Ready MICHAEL LEWIS
Service/Power Release 3/27/2024 Corrections Issued MICHAEL LEWIS
Smoke Detectors 3/27/2024 Approved MICHAEL LEWIS
ELECTRICAL-Final 2/20/2025 No Access for Inspection JOHN QUINTANILLA
Final 2/20/2025 No Access for Inspection JOHN QUINTANILLA
HVAC-Final 2/20/2025 No Access for Inspection JOHN QUINTANILLA
PLUMBING-Final 2/20/2025 No Access for Inspection JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 2/20/2025 SGSOV Not Ready JOHN QUINTANILLA
Service/Power Release 2/20/2025 No Access for Inspection JOHN QUINTANILLA
ELECTRICAL-Final 2/26/2025 Not Ready for Inspection JOHN QUINTANILLA
Final 2/26/2025 Not Ready for Inspection JOHN QUINTANILLA
HVAC-Final 2/26/2025 Approved JOHN QUINTANILLA
PLUMBING-Final 2/26/2025 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 2/26/2025 SGSOV Approved JOHN QUINTANILLA
Service/Power Release 2/26/2025 Not Ready for Inspection JOHN QUINTANILLA
ELECTRICAL-Final 3/3/2025 Approved JOHN QUINTANILLA
Final 3/3/2025 Not Ready for Inspection JOHN QUINTANILLA
HVAC-Final 3/3/2025 Approved JOHN QUINTANILLA
PLUMBING-Final 3/3/2025 Approved JOHN QUINTANILLA
Service/Power Release 3/3/2025 Approved JOHN QUINTANILLA
Service/Power Release 3/11/2025 No Access for Inspection JOHN QUINTANILLA