3469 S SYCAMORE AVE 90016

Certificate Information: 3469 S SYCAMORE AVE 90016

Application / Permit
22010-10000-00177
Plan Check / Job No.
B22LA00495
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT PORTION OF (E) DETACHED GARAGE INTO ADU AND LAUNDRY PER CA GC 65852.2(e)(1)(A).
Permit Issued
Issued on 4/8/2022
Issuing Office
Current Status
Issued on 4/8/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/14/2022 APPLICANT
Assigned to Plan Check Engineer 1/21/2022 VIVIAN LAO
Corrections Issued 1/21/2022 VIVIAN LAO
Applicant returned to address corrections 2/15/2022 VIVIAN LAO
Plan Check Approved 2/18/2022 JOE VO
Issued 4/8/2022 APPLICANT

Permit Application Clearance Information

Hold Cleared 1/21/2022 JEREMY CORONEL
Address approval Cleared 2/16/2022 CELINA MORENO
Roof/Waste drainage to street Cleared 2/16/2022 CELINA MORENO
Sewer availability Cleared 2/16/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 3/22/2022 AMY SHUM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 4/26/2022 Not Ready for Inspection JOSE AVILA
PLUMBING-Rough 4/26/2022 Partial Approval JOSE AVILA
Pre-Inspection 4/26/2022 Approved JOSE AVILA
Footing/Foundation/Slab 5/2/2022 Approved JOSE AVILA
PLUMBING-Rough 5/2/2022 Approved JOSE AVILA
ELECTRICAL-Rough 5/9/2022 Corrections Issued JOSE AVILA
HVAC-Rough 5/9/2022 Corrections Issued JOSE AVILA
Rough-Elec/Plmb/HVAC 5/17/2022 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 8/24/2022 Corrections Issued JOSE AVILA
Excavation/Setback/Form/Re-Bar 8/29/2022 Approved JOSE AVILA
Footing/Foundation/Slab 8/29/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 10/6/2022 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 10/6/2022 Approved JOSE AVILA
HVAC-Rough 10/6/2022 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 10/13/2022 Approved JOSE AVILA
HVAC-Rough 10/13/2022 Approved JOSE AVILA
Wood Frame 10/13/2022 Approved JOSE AVILA
ELECTRICAL-Rough 10/26/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 11/2/2022 Approved JOSE AVILA
Insulation 11/2/2022 Approved JOSE AVILA
Drywall Nailing 11/16/2022 Approved JOSE AVILA
Final 8/31/2023 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 8/31/2023 SGSOV No Gas JOSE AVILA
Smoke Detectors 8/31/2023 Approved JOSE AVILA
Final 9/7/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 9/12/2023 Corrections Issued JOSE AVILA
Final 10/3/2023 Corrections Issued JOSE AVILA