1623 W MANCHESTER AVE 90047

Certificate Information: 1623 W MANCHESTER AVE 90047

Application / Permit
22010-10000-00171
Plan Check / Job No.
B22LA00490
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
New 5-story, 50-unit (100% affordable) mixed-use apartment with 3 levels of Type VA apartment over 2 levels of Type IA apartments, office, parking and amenities using TOC Tier 3 incentives.
Permit Issued
Issued on 6/2/2022
Issuing Office
Metro
Current Status
CofO Corrected on 1/5/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/11/2022 APPLICANT
Assigned to Plan Check Engineer 1/20/2022 RODOLFO ARIAS
Corrections Issued 1/26/2022 RODOLFO ARIAS
Quality Review Completed 1/31/2022 EUGENE BARBEAU
Applicant returned to address corrections 5/20/2022 RODOLFO ARIAS
Plan Check Approved 6/2/2022 RODOLFO ARIAS
Issued 6/2/2022 APPLICANT
TCO Issued (Expire Date: 08-27-2025) 2/28/2025 ADAM BURGESS
TCO Issued (Expire Date: 03-01-2026) 9/2/2025 ADAM BURGESS
CofO in Progress 12/31/2025 JAMES POWERS
CofO Issued-Status Void 12/31/2025 ERNESTO CORRAL
Permit Finaled-Status Void 12/31/2025 ERNESTO CORRAL
Re-Activate Permit 1/5/2026 ERNESTO CORRAL
Permit Finaled 1/5/2026 ERNESTO CORRAL
Permit Finaled 1/5/2026 ERNESTO CORRAL
CofO Corrected 1/5/2026 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 1/25/2022 JEANETTE VONG
Community Plan Implem. Overlay Cleared 1/25/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 2/22/2022 JEANETTE VONG
Highway dedication Cleared 3/4/2022 JEANETTE VONG
Permit Cleared 3/4/2022 JEANETTE VONG
Sewer availability Cleared 3/15/2022 JEANETTE VONG
Building over 36-ft Cleared 3/22/2022 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 3/22/2022 CALOSHA APPROVED
Community Plan Implem. Overlay Cleared 3/24/2022 KEVIN ARUCAN
Driveway location Cleared 3/24/2022 KEVIN ARUCAN
Internal circulation Cleared 3/24/2022 KEVIN ARUCAN
Community Plan Implem. Overlay Cleared 4/8/2022 RIDWAN HARDY
Construction near power lines Cleared 4/8/2022 RIDWAN HARDY
Bicycle Parking Cleared 5/9/2022 JEREMY CHOK
Hydrant and Access approval Cleared 5/12/2022 KURT CORRAL
Low Impact Development Cleared 5/13/2022 MARTIN FRAGOSO
Site Plan review Cleared 5/13/2022 ANACANY HURTADO
Roof/Waste drainage to street Cleared 5/19/2022 JEANIE LAM
Historic Resource Verification Cleared 5/20/2022 MAX LODER
Public Housing Cleared 5/20/2022 JORGE ALCANTAR
DAS Clearance Cleared 5/23/2022 RODOLFO ARIAS
Green Code Cleared 5/23/2022 RODOLFO ARIAS
Community Plan Implem. Overlay Cleared 5/24/2022 RICHARD SANCHEZ
DCP conditions approval Cleared 5/24/2022 LOUIE MILLER
Density Bonus 12.22.A.31 Cleared 5/24/2022 LOUIE MILLER
Fire Marshal Fire Life Safety Cleared 5/24/2022 MENOA AGHAJANI
Frnt yard landscape/Water mgmt Cleared 5/24/2022 MAXFIELD VERMY
Miscellaneous Cleared 5/24/2022 MAXFIELD VERMY
Miscellaneous Cleared 5/24/2022 MAXFIELD VERMY
Opn space landscape/Water mgmt Cleared 5/24/2022 MAXFIELD VERMY
Prkng lot landscape/Water mgmt Cleared 5/24/2022 MAXFIELD VERMY
Trees in Parkway Cleared 5/24/2022 RICHARD SANCHEZ
Work Adjacent to Public Way Cleared 5/24/2022 KHOUNG LE
ZA Case Cleared 5/24/2022 MAXFIELD VERMY
Community Plan Implem. Overlay Cleared 5/26/2022 HELEN JADALI
Encroachment in public way Cleared 5/26/2022 JEREMY CHOK
Miscellaneous Cleared 5/26/2022 HELEN JADALI
Miscellaneous Cleared 5/26/2022 HELEN JADALI
Miscellaneous Cleared 5/26/2022 HELEN JADALI
Redevelopment Project Area Cleared 5/26/2022 DAVID URITA

Contact Information

Architect Withee,, Dan Richard; Lic. No.: NA9049       ,
Contractor Portrait Construction Inc; Lic. No.: 977636-B 265 N JOY STREET #200      CORONA, CA 92879
Engineer Cunningham,, William Charbern; Lic. No.: C80129 2745 PARKVIEW DRIVE      THOUSAND OAKS, CA 91362
Engineer Derkalousdian,, Hrair Harry; Lic. No.: C79694 3622 VIRGINIA STREET      GLENDALE, CA 91214
Engineer Eosakul,, Dissakorn; Lic. No.: S5226 8363 EDGEWOOD ST      CHINO, CA 91708
Engineer Zen,, Petrina; Lic. No.: C87489 905 PIEDMONT      IRVINE, CA 92620
Geologist Kirkgard,, Susan Franzen; Lic. No.: EG1754 1481 STONEBROOK STREET      AZUSA, CA 91702
Landscape Architect Cicchetti,, Jon David; Lic. No.: LA2191 140 LINDEN AVE STE 286      LONG BEACH, CA 90802

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 11/22/2022 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 12/21/2022 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 12/23/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/21/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 2/22/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 3/7/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 3/8/2023 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 3/8/2023 Partial Approval JAMES POWERS
Footing/Foundation/Slab 3/8/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/9/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/30/2023 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 3/30/2023 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 4/6/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/6/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 4/6/2023 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 4/6/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/14/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 4/14/2023 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 4/14/2023 Partial Approval JAMES POWERS
Green Building Rough 4/18/2023 Partial Inspection GREGORY POMISH
Reinforced Concrete Frame 4/18/2023 Not Ready for Inspection GREGORY POMISH
Structural Steel Frame 4/18/2023 Not Ready for Inspection GREGORY POMISH
Verify Sprinkler Sign Off 4/18/2023 Not Ready for Inspection GREGORY POMISH
Footing/Foundation/Slab 4/20/2023 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 4/21/2023 Conditional Approval LARRY ARNICK
Deputy Shotcrete 4/21/2023 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 4/21/2023 Partial Approval LARRY ARNICK
Deputy Shotcrete 4/26/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Methane Barrier 4/27/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 4/28/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 5/1/2023 Partial Approval JAMES POWERS
Green Building Rough 5/1/2023 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 5/1/2023 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 5/1/2023 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 5/5/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Shotcrete 5/5/2023 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 5/5/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 5/9/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 5/10/2023 Conditional Approval MICHAEL ROSENBERG
Reinforced Concrete Frame 5/10/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/15/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 5/15/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 5/16/2023 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 5/16/2023 Partial Approval LARRY ARNICK
Masonry Wall/Backfill 5/16/2023 Partial Approval LARRY ARNICK
Deputy Reinf. Concrete 5/17/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 5/17/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 5/18/2023 Partial Approval JAMES POWERS
Green Building Rough 5/18/2023 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 5/18/2023 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 5/18/2023 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 5/19/2023 Partial Approval JAMES POWERS
Footing/Foundation/Slab 5/19/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/22/2023 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 5/22/2023 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Masonry 6/1/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 6/2/2023 Conditional Approval TED RIES
Green Building Rough 6/2/2023 Partial Inspection TED RIES
Masonry Wall/Backfill 6/2/2023 Partial Approval TED RIES
Reinforced Masonry Frame 6/2/2023 Partial Approval TED RIES
Verify Sprinkler Sign Off 6/2/2023 Approved TED RIES
Deputy Reinf. Masonry 6/5/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 6/9/2023 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 6/9/2023 Partial Approval JAMES POWERS
Footing/Foundation/Slab 6/9/2023 Partial Approval JAMES POWERS
Green Building Rough 6/9/2023 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 6/9/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/12/2023 Partial Approval JAMES POWERS
Green Building Rough 6/20/2023 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 6/20/2023 Partial Approval JAMES POWERS
Structural Steel Frame 6/20/2023 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 6/21/2023 Partial Approval JAMES POWERS
Footing/Foundation/Slab 6/21/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/27/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 6/28/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 7/10/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/11/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/14/2023 Partial Approval JAMES POWERS
Green Building Rough 7/14/2023 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 7/14/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/24/2023 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/24/2023 Partial Approval JAMES POWERS
Green Building Rough 7/24/2023 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 7/24/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/26/2023 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/26/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/15/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/16/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/17/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/18/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/23/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/24/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/25/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/28/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/29/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/31/2023 Partial Approval JAMES POWERS
Green Building Rough 8/31/2023 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 8/31/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/1/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/12/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/13/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/14/2023 Conditional Approval LARRY ARNICK
Green Building Rough 9/14/2023 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 9/14/2023 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 9/15/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/18/2023 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 9/18/2023 Partial Approval JAMES POWERS
Green Building Rough 9/18/2023 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 9/18/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/20/2023 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/20/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/21/2023 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/21/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/22/2023 Conditional Approval LARRY ARNICK
Deputy Reinf. Masonry 9/22/2023 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 9/22/2023 Not Ready for Inspection LARRY ARNICK
Green Building Rough 9/22/2023 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 9/22/2023 Partial Approval LARRY ARNICK
Deputy Drilled-In Anchors 9/25/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/25/2023 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/25/2023 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/26/2023 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/27/2023 Conditional Approval LARRY ARNICK
Deputy Wood Construction 9/27/2023 Conditional Approval MICHAEL ROSENBERG
Green Building Rough 9/27/2023 Partial Approval LARRY ARNICK
Masonry Wall/Backfill 9/27/2023 Partial Approval LARRY ARNICK
Wood Frame 9/27/2023 Partial Approval LARRY ARNICK
Deputy Drilled-In Anchors 9/28/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/28/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 9/28/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/28/2023 Partial Approval JAMES POWERS
Reinforced Masonry Frame 9/28/2023 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/29/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/2/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/3/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/4/2023 Conditional Approval RAFAEL ESPINOZA
Green Building Rough 10/4/2023 Not Ready for Inspection RAFAEL ESPINOZA
Reinforced Masonry Frame 10/4/2023 Partial Approval RAFAEL ESPINOZA
Wood Frame 10/4/2023 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Reinf. Concrete 10/5/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/6/2023 Partial Approval JAMES POWERS
Reinforced Concrete Frame 10/6/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 10/10/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 10/10/2023 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/16/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 10/16/2023 Partial Approval JAMES POWERS
Green Building Rough 10/16/2023 Not Ready for Inspection JAMES POWERS
Wood Frame 10/16/2023 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Masonry 10/17/2023 Conditional Approval LARRY ARNICK
Deputy Wood Construction 10/17/2023 Conditional Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 10/17/2023 Partial Approval LARRY ARNICK
Deputy Reinf. Masonry 10/18/2023 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/19/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 10/19/2023 Partial Approval JAMES POWERS
Reinforced Concrete Frame 10/19/2023 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/20/2023 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/23/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 10/24/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 10/25/2023 Conditional Approval LARRY ARNICK
Masonry Wall/Backfill 10/25/2023 Partial Approval LARRY ARNICK
Deputy Reinf. Masonry 10/26/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 10/26/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 10/30/2023 Conditional Approval LARRY ARNICK
Green Building Rough 10/30/2023 Not Ready for Inspection LARRY ARNICK
Wood Frame 10/30/2023 Partial Approval LARRY ARNICK
Deputy Reinf. Masonry 10/31/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 10/31/2023 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 11/1/2023 Conditional Approval LARRY ARNICK
Deputy Wood Construction 11/1/2023 Conditional Approval LARRY ARNICK
Masonry Wall/Backfill 11/1/2023 Partial Approval LARRY ARNICK
Wood Frame 11/1/2023 Partial Approval LARRY ARNICK
Deputy Reinf. Masonry 11/2/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Wood Construction 11/2/2023 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 11/3/2023 Conditional Approval LARRY ARNICK
Deputy Wood Construction 11/3/2023 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 11/6/2023 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 11/6/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/7/2023 Conditional Approval LARRY ARNICK
Deputy Wood Construction 11/7/2023 Conditional Approval LARRY ARNICK
Green Building Rough 11/7/2023 Not Ready for Inspection LARRY ARNICK
Wood Frame 11/7/2023 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 11/8/2023 Conditional Approval LARRY ARNICK
Deputy Wood Construction 11/8/2023 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 11/8/2023 Partial Approval LARRY ARNICK
Reinforced Concrete Frame 11/8/2023 Partial Approval LARRY ARNICK
Deputy Reinf. Concrete 11/9/2023 Conditional Approval LARRY ARNICK
Deputy Wood Construction 11/9/2023 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 11/9/2023 Partial Approval LARRY ARNICK
Footing/Foundation/Slab 11/9/2023 Partial Approval LARRY ARNICK
T-Bar Ceiling 11/9/2023 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 11/13/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/14/2023 Conditional Approval LARRY ARNICK
Deputy Wood Construction 11/14/2023 Conditional Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 11/14/2023 Not Ready for Inspection LARRY ARNICK
Green Building Rough 11/14/2023 Not Ready for Inspection LARRY ARNICK
Wood Frame 11/14/2023 Not Ready for Inspection LARRY ARNICK
Insulation 11/22/2023 Not Ready for Inspection LARRY ARNICK
Insulation 11/28/2023 Approved DARRYL ARNOLD
Deputy Reinf. Concrete 11/29/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/30/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/1/2023 Partial Approval JAMES POWERS
Reinforced Concrete Frame 12/1/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/4/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/5/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/6/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/7/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/8/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/11/2023 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 12/11/2023 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 12/12/2023 Partial Approval JAMES POWERS
Reinforced Concrete Frame 12/12/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/13/2023 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 12/14/2023 Not Ready for Inspection LARRY ARNICK
Deputy Reinf. Concrete 12/15/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 12/20/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 12/21/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 12/22/2023 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 12/22/2023 Not Ready for Inspection JAMES POWERS
Green Building Rough 12/22/2023 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 12/22/2023 Partial Approval JAMES POWERS
Deputy Shotcrete 12/26/2023 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/5/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/8/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/9/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/10/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/11/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/12/2024 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 1/12/2024 Partial Approval JAMES POWERS
Green Building Rough 1/12/2024 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 1/12/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/16/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 1/19/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 2/2/2024 Conditional Approval MICHAEL ROSENBERG
Green Building Rough 2/2/2024 Not Ready for Inspection LARRY ARNICK
Wood Frame 2/2/2024 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 2/13/2024 Partial Approval LARRY ARNICK
Green Building Rough 2/13/2024 Not Ready for Inspection LARRY ARNICK
Wood Frame 2/13/2024 Not Ready for Inspection LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 2/14/2024 Partial Approval LARRY ARNICK
Deputy Wood Construction 2/15/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Masonry 2/23/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/26/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/27/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/28/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/29/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/29/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/5/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/6/2024 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 3/6/2024 Not Ready for Inspection LARRY ARNICK
Green Building Rough 3/6/2024 Not Ready for Inspection LARRY ARNICK
Masonry Wall/Backfill 3/6/2024 Partial Approval LARRY ARNICK
Reinforced Masonry Frame 3/6/2024 Partial Approval LARRY ARNICK
Deputy Reinf. Masonry 3/7/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/8/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/11/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/12/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/13/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/14/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/15/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/18/2024 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 3/18/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/26/2024 Partial Approval JAMES POWERS
Insulation 3/26/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/29/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 3/29/2024 Partial Approval JAMES POWERS
Green Building Rough 3/29/2024 Not Ready for Inspection JAMES POWERS
Insulation 3/29/2024 Partial Approval JAMES POWERS
Wood Frame 3/29/2024 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 4/2/2024 Partial Approval JAMES POWERS
Insulation 4/3/2024 Partial Approval JAMES POWERS
Drywall Nailing 4/5/2024 Partial Approval JAMES POWERS
Green Building Rough 4/5/2024 Not Ready for Inspection JAMES POWERS
Insulation 4/5/2024 Partial Approval JAMES POWERS
Masonry Wall/Backfill 4/5/2024 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 4/19/2024 Partial Approval JAMES POWERS
Insulation 4/19/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 4/23/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/23/2024 Partial Approval JAMES POWERS
Green Building Rough 4/23/2024 Approved JAMES POWERS
Wood Frame 4/23/2024 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Masonry 4/30/2024 Partial Approval JAMES POWERS
Insulation 5/1/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/3/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/6/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/7/2024 Partial Approval JAMES POWERS
Drywall Nailing 5/7/2024 Partial Approval JAMES POWERS
Masonry Wall/Backfill 5/7/2024 Partial Approval JAMES POWERS
Deputy Fireproofing 6/7/2024 Partial Approval JAMES POWERS
Drywall Nailing 6/13/2024 Partial Approval JAMES POWERS
Insulation 6/13/2024 Partial Approval JAMES POWERS
Deputy Fireproofing 6/18/2024 Partial Approval JAMES POWERS
Drywall Nailing 6/24/2024 Partial Approval JAMES POWERS
Drywall Nailing 7/10/2024 Not Ready for Inspection JAMES POWERS
Insulation 7/10/2024 Partial Approval JAMES POWERS
Interior/Exterior Lathing 7/17/2024 Partial Approval JAMES POWERS
Drywall Nailing 7/19/2024 Partial Approval JAMES POWERS
Drywall Nailing 7/25/2024 Partial Approval JAMES POWERS
Insulation 7/25/2024 Partial Approval JAMES POWERS
Insulation 8/9/2024 Partial Approval JAMES POWERS
Drywall Nailing 8/16/2024 Not Ready for Inspection JAMES POWERS
Insulation 8/16/2024 Partial Approval JAMES POWERS
Interior/Exterior Lathing 8/16/2024 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 8/16/2024 Partial Approval JAMES POWERS
Interior/Exterior Lathing 8/19/2024 Partial Approval JAMES POWERS
Drywall Nailing 8/21/2024 Partial Approval JAMES POWERS
Interior/Exterior Lathing 8/21/2024 Not Ready for Inspection JAMES POWERS
Insulation 8/22/2024 Partial Approval JAMES POWERS
Drywall Nailing 8/26/2024 Partial Approval JAMES POWERS
Insulation 8/28/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 8/28/2024 Partial Approval JAMES POWERS
Drywall Nailing 9/11/2024 Partial Approval JAMES POWERS
Insulation 9/11/2024 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 9/11/2024 Partial Approval JAMES POWERS
Drywall Nailing 9/19/2024 Not Ready for Inspection JAMES POWERS
Insulation 9/19/2024 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 9/19/2024 Partial Approval JAMES POWERS
Interior/Exterior Lathing 9/20/2024 Not Ready for Inspection JAMES POWERS
Deputy Drilled-In Anchors 9/23/2024 Partial Approval JAMES POWERS
Footing/Foundation/Slab 9/25/2024 Partial Approval JAMES POWERS
Insulation 9/25/2024 Partial Approval JAMES POWERS
Drywall Nailing 9/30/2024 Partial Approval JAMES POWERS
Drywall Nailing 10/11/2024 Partial Approval RONALD JIMENEZ
Drywall Nailing 10/16/2024 Partial Approval LARRY ARNICK
Masonry Wall/Backfill 10/16/2024 Approved LARRY ARNICK
Drywall Nailing 11/12/2024 Partial Approval LARRY ARNICK
Drywall Nailing 12/5/2024 Partial Approval JAMES POWERS
Drywall Nailing 12/17/2024 Partial Approval JAMES POWERS
Final 12/19/2024 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 12/19/2024 Approved JAMES POWERS
Green Building Final 12/19/2024 Approved JAMES POWERS
Insulation 12/19/2024 Partial Approval JAMES POWERS
Reinforced Concrete Frame 12/19/2024 Approved JAMES POWERS
Reinforced Masonry Frame 12/19/2024 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 12/19/2024 SGSOV Not Ready JAMES POWERS
Smoke Detectors 12/19/2024 Approved JAMES POWERS
Structural Steel Frame 12/19/2024 Approved JAMES POWERS
Wood Frame 12/19/2024 Approved JAMES POWERS
Insulation 12/20/2024 Not Ready for Inspection JAMES POWERS
Drywall Nailing 12/26/2024 Partial Approval JAMES POWERS
Drywall Nailing 2/12/2025 Approved JAMES POWERS
Final 2/12/2025 OK for TCO JAMES POWERS
SGSOV-Seismic Gas S/O Valve 2/12/2025 SGSOV Approved JAMES POWERS
Deputy Drilled-In Anchors 2/20/2025 Conditional Approval DARRYL ARNOLD
Deputy Wood Construction 2/20/2025 Conditional Approval DARRYL ARNOLD
Light Gage Steel Frame 2/25/2025 Partial Approval LARRY ARNICK
Special/Order Compliance 7/30/2025 Partial Approval JAMES POWERS
Final 12/11/2025 Not Ready for Inspection JAMES POWERS
Final 12/22/2025 Not Ready for Inspection JAMES POWERS
Deputy Steel/Welding 12/30/2025 Partial Approval JAMES POWERS
Pre-Inspection 12/30/2025 Approved ALFREDO LOPEZ
Deputy Drilled-In Anchors 12/31/2025 Partial Approval JAMES POWERS
Deputy Fireproofing 12/31/2025 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/31/2025 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 12/31/2025 Partial Approval JAMES POWERS
Deputy Shotcrete 12/31/2025 Partial Approval JAMES POWERS
Deputy Steel/Welding 12/31/2025 Partial Approval JAMES POWERS
Deputy Wood Construction 12/31/2025 Partial Approval JAMES POWERS
Final 12/31/2025 OK to Issue CofO JAMES POWERS