12312 N LITHUANIA DR 91344

Certificate Information: 12312 N LITHUANIA DR 91344

Application / Permit
22010-10000-00120
Plan Check / Job No.
B22LA00430
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 1200 SQFT ADU AT REAR OF LOT
Permit Issued
Issued on 8/3/2022
Issuing Office
Current Status
CofO Issued on 3/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/11/2022 APPLICANT
Assigned to Plan Check Engineer 2/8/2022 JAD BASMA
Corrections Issued 2/11/2022 JAD BASMA
Quality Review Completed 2/16/2022 KEN GILL
Building Plans Picked Up 2/25/2022 APPLICANT
Plan Check Approved 8/3/2022 JAD BASMA
Issued 8/3/2022 APPLICANT
CofO in Progress 3/17/2023 DAVID SCANTLIN
Permit Finaled 3/24/2023 JOHN JANSON
CofO Issued 3/24/2023 JOHN JANSON
Permit Finaled 3/24/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/8/2022 LEE GUILBEAUX
Address approval Cleared 3/8/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 3/8/2022 LEE GUILBEAUX
Sewer availability Cleared 3/8/2022 LEE GUILBEAUX
Low Impact Development Cleared 7/8/2022 JULIAN SUNG
Roof/Waste drainage to street Cleared 7/15/2022 DAGOVERTO GUERRERO
Construction near power lines Cleared 7/21/2022 TINA MIRANDA
GPI Written Notices Cleared 8/3/2022 JAD BASMA
Grading Pre-Inspection Cleared 8/3/2022 JAD BASMA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/17/2022 Not Ready for Inspection DAVID SCANTLIN
Underground Mechanical 8/22/2022 Approved SEAN HAUPT
Excavation/Setback/Form/Re-Bar 9/2/2022 Approved DAVID SCANTLIN
Special/Order Compliance 9/2/2022 Approved SEAN WIRCH
BUILDING-Rough-Frame 10/24/2022 Approved SEAN HAUPT
ELECTRICAL-Rough 10/24/2022 Approved SEAN HAUPT
Green Building Rough 10/24/2022 Approved SEAN HAUPT
HVAC-Rough 10/24/2022 Approved SEAN HAUPT
PLUMBING-Rough 10/24/2022 Approved SEAN HAUPT
Final 11/1/2022 Corrections Issued SEAN WIRCH
Insulation 11/1/2022 Approved SEAN WIRCH
Interior/Exterior Lathing 11/1/2022 Partial Approval SEAN WIRCH
Drywall Nailing 11/7/2022 Not Ready for Inspection JUSTIN HAWLEY
Drywall Nailing 11/8/2022 Approved KRISTEN CAUSEY
Shower Pan 11/22/2022 Approved DAVID SCANTLIN
Final 2/24/2023 Corrections Issued DAVID SCANTLIN
Footing/Foundation/Slab 2/24/2023 Approved DAVID SCANTLIN
Green Building Final 2/24/2023 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 2/24/2023 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 2/24/2023 Approved DAVID SCANTLIN
Final 3/17/2023 OK to Issue CofO DAVID SCANTLIN
Special/Order Compliance 3/17/2023 Partial Inspection MORRIS JACKSON