1463 3/4 E 109TH ST 90059

Certificate Information: 1463 3/4 E 109TH ST 90059

Application / Permit
22010-10000-00089
Plan Check / Job No.
B22LA00299
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) DETACHED ADU (2-STORY) PER LAMC 12.22 A.33 (c) & (d) 2 OF 2
Permit Issued
Issued on 10/2/2024
Issuing Office
Metro
Current Status
CofO Issued on 5/6/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/7/2022 APPLICANT
Assigned to Plan Check Engineer 1/20/2022 ADRIANA LOPEZ
Corrections Issued 2/2/2022 ADRIANA LOPEZ
Quality Review Completed 2/7/2022 SAI KHUM
Building Plans Picked Up 2/9/2022 APPLICANT
Applicant returned to address corrections 3/15/2023 ADRIANA LOPEZ
Applicant returned to address corrections 3/21/2023 ADRIANA LOPEZ
Plan Check Approved 5/12/2023 ADRIANA LOPEZ
Issued 10/2/2024 APPLICANT
CofO in Progress 5/6/2026 ANSON MAGLASANG
Permit Finaled 5/6/2026 ANSON MAGLASANG
CofO Issued 5/6/2026 ANSON MAGLASANG
Permit Finaled 5/6/2026 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 2/16/2022 CELINA MORENO
Hydrant and Access approval Cleared 3/16/2022 CINDY JOSSELYN
Eng Process Fee Ord 176,300 Cleared 7/15/2022 JEANETTE VONG
Low Impact Development Cleared 12/14/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 12/22/2022 JEANETTE VONG
Sewer availability Cleared 1/4/2023 CINDY QI

Contact Information

Contractor Owner-Builder       ,
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/19/2024 Corrections Issued ANTHONY EGSON
Underground Mechanical 12/19/2024 Not Ready for Inspection ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 12/24/2024 Approved ANTHONY EGSON
Underground Mechanical 12/24/2024 Partial Approval ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 1/2/2025 Approved EUGENE CASSIDY
Footing/Foundation/Slab 1/2/2025 Approved EUGENE CASSIDY
Sewer 1/13/2025 Partial Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 1/22/2025 Partial Approval JOSEPH MCGARRY
Green Building Rough 1/22/2025 Not Ready for Inspection JOSEPH MCGARRY
Verify Sprinkler Sign Off 1/22/2025 Not Ready for Inspection JOSEPH MCGARRY
Pre-Inspection 1/23/2025 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 2/19/2025 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 2/24/2025 Partial Approval BEN MOLSTAD
Underground Mechanical 3/10/2025 Approved ANTHONY EGSON
BUILDING-Rough-Frame 4/2/2025 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 4/2/2025 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 4/2/2025 Corrections Issued ANTHONY EGSON
HVAC-Rough 4/2/2025 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 4/2/2025 Not Ready for Inspection ANTHONY EGSON
Verify Sprinkler Sign Off 4/2/2025 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 5/6/2025 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 5/6/2025 Not Ready for Inspection ANTHONY EGSON
HVAC-Rough 5/6/2025 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 5/6/2025 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 5/7/2025 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 5/8/2025 Partial Approval ANTHONY EGSON
HVAC-Rough 5/9/2025 Approved ANTHONY EGSON
PLUMBING-Rough 5/9/2025 Approved ANTHONY EGSON
ELECTRICAL-Rough 5/12/2025 Approved ANTHONY EGSON
Interior/Exterior Lathing 6/6/2025 Approved JOHN KLARIN
Insulation 6/13/2025 Approved ANTHONY EGSON
Insulation 6/16/2025 No Access for Inspection ANTHONY EGSON
Drywall Nailing 6/23/2025 Approved ANTHONY EGSON
Green Building Rough 6/23/2025 Approved ANTHONY EGSON
Shower Pan 8/8/2025 Corrections Issued ANTHONY EGSON
Shower Pan 8/20/2025 Approved ANTHONY EGSON
Interior/Exterior Lathing 8/27/2025 Approved ANTHONY EGSON
Shower Pan 8/27/2025 Approved ANTHONY EGSON
BUILDING-Rough-Frame 3/18/2026 Approved ARTHUR NEGRETE
Final 3/18/2026 Not Ready for Inspection ARTHUR NEGRETE
Green Building Final 3/18/2026 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 3/18/2026 SGSOV Not Required ARTHUR NEGRETE
Service/Power Release 3/18/2026 Approved ARTHUR NEGRETE
Smoke Detectors 3/18/2026 Approved ARTHUR NEGRETE
Verify Sprinkler Sign Off 3/18/2026 Approved ARTHUR NEGRETE
ELECTRICAL-Final 4/17/2026 Approved ARTHUR NEGRETE
Final 4/17/2026 OK to Issue CofO ARTHUR NEGRETE
HVAC-Final 4/17/2026 Approved ARTHUR NEGRETE
PLUMBING-Final 4/17/2026 Approved ARTHUR NEGRETE