947 S WESTCHESTER PL 90019
Certificate Information: 947 S WESTCHESTER PL 90019
- Application / Permit
- 22010-10000-00080
- Plan Check / Job No.
- B22LA00271
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW TWO STORY ACCESSORY DWELLING UNIT WITH ATTACHED GARAGE
- Permit Issued
- Issued on 8/1/2023
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 5/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/20/2022 | JOHNNY WU |
| Corrections Issued | 1/26/2022 | JOHNNY WU |
| Quality Review Completed | 1/27/2022 | FARUK SEZER |
| Building Plans Picked Up | 1/31/2022 | APPLICANT |
| Applicant returned to address corrections | 4/11/2022 | JOHNNY WU |
| Applicant returned to address corrections | 4/12/2022 | JOHNNY WU |
| Plan Check Approved | 7/6/2022 | JOHNNY WU |
| Issued | 8/1/2023 | APPLICANT |
| CofO in Progress | 4/10/2024 | JEFFREY MEAD |
| Permit Finaled | 5/6/2024 | DEROLD HAUFF |
| CofO Issued | 5/6/2024 | DEROLD HAUFF |
| Permit Finaled | 5/6/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 1/22/2022 | JOHNNY WU |
| Address approval | Cleared | 3/15/2022 | STEVE MELGAR |
| Address approval | Cleared | 3/15/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 4/4/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 4/4/2022 | STEVE MELGAR |
| HPOZ | Cleared | 6/2/2022 | AMANDA KAINER |
| Miscellaneous | Cleared | 6/2/2022 | AMANDA KAINER |
| Miscellaneous | Cleared | 6/2/2022 | AMANDA KAINER |
| Low Impact Development | Cleared | 6/13/2022 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 6/15/2022 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 6/20/2022 | CINDY JOSSELYN |
| Green Code | Cleared | 8/1/2023 | JOHNNY WU |
Contact Information
| Contractor | Goliath Construction; Lic. No.: 1056541-B | 6914 RADFORD AVE NORTH HOLLYWOOD, CA 91605 |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/9/2023 | Partial Inspection | JEFFREY MEAD |
| Underground Mechanical | 8/9/2023 | Approved | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 8/11/2023 | Approved | JEFFREY MEAD |
| Footing/Foundation/Slab | 8/11/2023 | Approved | JEFFREY MEAD |
| Deputy Wood Construction | 8/28/2023 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2023 | Partial Approval | JEFFREY MEAD |
| Deputy Wood Construction | 10/4/2023 | Partial Approval | JEFFREY MEAD |
| ELECTRICAL-Rough | 10/5/2023 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2023 | Partial Approval | JEFFREY MEAD |
| PLUMBING-Rough | 10/5/2023 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2023 | Approved | JEFFREY MEAD |
| HVAC-Rough | 10/10/2023 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 10/20/2023 | Corrections Issued | SCOTT FINNILA |
| Gas Test | 10/20/2023 | Partial Inspection | SCOTT FINNILA |
| Green Building Rough | 10/20/2023 | Corrections Issued | SCOTT FINNILA |
| Interior/Exterior Lathing | 10/20/2023 | Corrections Issued | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 10/20/2023 | Partial Inspection | SCOTT FINNILA |
| Insulation | 10/25/2023 | Corrections Issued | JEFFREY MEAD |
| Insulation | 11/14/2023 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 11/14/2023 | Approved | JEFFREY MEAD |
| Shower Pan | 11/14/2023 | Approved | JEFFREY MEAD |
| Drywall Nailing | 11/16/2023 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 11/17/2023 | Approved | JEFFREY MEAD |
| Gas Test | 1/9/2024 | Approved | JEFFREY MEAD |
| Sewer | 1/9/2024 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 1/10/2024 | Corrections Issued | JEFFREY MEAD |
| Gas Test | 1/10/2024 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 1/10/2024 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 1/24/2024 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 4/9/2024 | Approved | JEFFREY MEAD |
| Final | 4/9/2024 | OK to Issue CofO | JEFFREY MEAD |
| Green Building Final | 4/9/2024 | Approved | JEFFREY MEAD |
| Green Building Rough | 4/9/2024 | Approved | JEFFREY MEAD |
| HVAC-Final | 4/9/2024 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 4/9/2024 | SGSOV Approved | JEFFREY MEAD |
| Service/Power Release | 4/9/2024 | Approved | JEFFREY MEAD |
| Smoke Detectors | 4/9/2024 | Approved | JEFFREY MEAD |
| Verify Sprinkler Sign Off | 4/9/2024 | Approved | JEFFREY MEAD |
| Special/Order Compliance | 4/29/2024 | Corrections Issued | JEFFREY MEAD |