122-122 1/2 E 36TH ST 90011

Certificate Information: 122-122 1/2 E 36TH ST 90011

Application / Permit
22010-10000-00072
Plan Check / Job No.
B22LA00240
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 3 STORY DUPLEX WITH ATTACHED GARAGE (REAR)
Permit Issued
Issued on 1/9/2023
Issuing Office
Metro
Current Status
CofO Issued on 11/30/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/10/2022 APPLICANT
Assigned to Plan Check Engineer 1/20/2022 STARR CHEN
Corrections Issued 1/23/2022 STARR CHEN
Quality Review Completed 1/25/2022 EUGENE BARBEAU
Building Plans Picked Up 3/2/2022 APPLICANT
Applicant returned to address corrections 3/15/2022 STARR CHEN
Plan Check Approved 11/15/2022 STARR CHEN
Issued 1/9/2023 APPLICANT
CofO in Progress 11/25/2023 ALEJANDRO DE ARTOLA
Permit Finaled 11/30/2023 DEROLD HAUFF
Permit Finaled 11/30/2023 DEROLD HAUFF
CofO Issued 11/30/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/7/2022 JEANETTE VONG
Roof/Waste drainage to street Cleared 3/15/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 9/7/2022 JEANETTE VONG
Frnt yard landscape/Water mgmt Cleared 9/7/2022 SPENCER WEJROWSKI
Sewer availability Cleared 9/7/2022 JEANETTE VONG
Low Impact Development Cleared 11/7/2022 LONDY ALVARADO
Hydrant and Access approval Cleared 11/12/2022 JOHN CONNEALLY

Contact Information

Contractor Pacific Coast Builders; Lic. No.: 834794-B 9277OTTO ST      DOWNEY, CA 90240
Engineer Elia,, Victor Anthony; Lic. No.: C64803 40912 CARLENA LN      TEMECULA, CA 92591
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/25/2023 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 1/25/2023 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 1/31/2023 Approved BRENDAN MORELLI
Deputy Steel/Welding 2/10/2023 Conditional Approval BRENDAN MORELLI
Deputy Wood Construction 2/13/2023 Conditional Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 2/13/2023 Partial Approval BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 2/17/2023 Partial Approval BRENDAN MORELLI
Deputy Wood Construction 4/26/2023 Approved BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 4/26/2023 Approved BRENDAN MORELLI
HVAC-Rough 5/8/2023 Approved BRENDAN MORELLI
PLUMBING-Rough 5/8/2023 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 5/10/2023 Conditional Approval BRENDAN MORELLI
ELECTRICAL-Rough 5/10/2023 Approved BRENDAN MORELLI
Green Building Rough 5/10/2023 Not Ready for Inspection BRENDAN MORELLI
Verify Sprinkler Sign Off 5/10/2023 Approved BRENDAN MORELLI
Insulation 5/17/2023 Approved BRENDAN MORELLI
Interior/Exterior Lathing 5/17/2023 Partial Approval BRENDAN MORELLI
Shower Pan 5/17/2023 Approved BRENDAN MORELLI
Drywall Nailing 5/25/2023 Approved STUART CHAPMAN
Interior/Exterior Lathing 5/25/2023 Approved STUART CHAPMAN
Gas Test 8/3/2023 Partial Approval ALEJANDRO DE ARTOLA
Sewer 8/3/2023 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 8/3/2023 Approved ALEJANDRO DE ARTOLA
Verify Rec and Parks Fee Memo 8/3/2023 Approved ALEJANDRO DE ARTOLA
Gas Test 10/2/2023 Approved ALEJANDRO DE ARTOLA
Verify Rec and Parks Fee Memo 10/2/2023 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 11/20/2023 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 11/20/2023 Approved ALEJANDRO DE ARTOLA
Final 11/20/2023 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 11/20/2023 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 11/20/2023 Approved ALEJANDRO DE ARTOLA
HVAC-Final 11/20/2023 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 11/20/2023 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 11/20/2023 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 11/20/2023 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 11/20/2023 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 11/22/2023 Approved ALEJANDRO DE ARTOLA
Final 11/22/2023 OK to Issue CofO ALEJANDRO DE ARTOLA
Green Building Final 11/22/2023 Approved ALEJANDRO DE ARTOLA
HVAC-Final 11/22/2023 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 11/22/2023 Approved ALEJANDRO DE ARTOLA
Service/Power Release 11/22/2023 Approved ALEJANDRO DE ARTOLA