2823-2823 1/2 S MAPLE AVE 90011

Certificate Information: 2823-2823 1/2 S MAPLE AVE 90011

Application / Permit
22010-10000-00069
Plan Check / Job No.
B22LA00233
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 3-STORY DUPLEX FRONT BUILDING "COMPLY WITH DEPARTMENT ORDER effective date 08/08/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 12/20/2023
Issuing Office
Metro
Current Status
CofO Issued on 1/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/11/2022 APPLICANT
Assigned to Plan Check Engineer 1/20/2022 MAHNAZ NOURHASHEMI
Corrections Issued 1/26/2022 MAHNAZ NOURHASHEMI
Quality Review Completed 2/4/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 2/9/2022 APPLICANT
Plan Check Approved 8/25/2022 MAHNAZ NOURHASHEMI
Issued 12/20/2023 APPLICANT
CofO in Progress 12/31/2024 ALEJANDRO DE ARTOLA
Permit Finaled 1/2/2025 DEROLD HAUFF
Permit Finaled 1/2/2025 DEROLD HAUFF
CofO Issued 1/2/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/11/2022 TREVOR QUAN
Low Impact Development Cleared 3/1/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 3/2/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 3/3/2022 TREVOR QUAN
Sewer availability Cleared 3/3/2022 TREVOR QUAN
Highway dedication Cleared 3/15/2022 TREVOR QUAN
Frnt yard landscape/Water mgmt Cleared 3/17/2022 LOUIS ORTEGA
Hydrant and Access approval Cleared 4/19/2022 JOHN CONNEALLY

Contact Information

Contractor Pacific Coast Builders; Lic. No.: 834794-B 9277OTTO ST      DOWNEY, CA 90240
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/17/2024 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 1/17/2024 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 1/19/2024 Approved ALEJANDRO DE ARTOLA
METHANE-Barrier 1/19/2024 Approved ALEJANDRO DE ARTOLA
METHANE-Subgrade 1/19/2024 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 2/8/2024 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 2/16/2024 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/27/2024 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/28/2024 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 5/17/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 5/17/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 5/17/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 5/20/2024 Approved ALEJANDRO DE ARTOLA
Green Building Rough 5/20/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 5/20/2024 Approved ALEJANDRO DE ARTOLA
METHANE-Rough 5/20/2024 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 5/21/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 5/21/2024 Approved ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 5/21/2024 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 5/24/2024 Approved ALEJANDRO DE ARTOLA
Insulation 5/24/2024 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 5/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 6/3/2024 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 6/4/2024 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 7/9/2024 Approved ALEJANDRO DE ARTOLA
Shower Pan 7/11/2024 Approved ALEJANDRO DE ARTOLA
Gas Test 7/18/2024 Partial Approval ALEJANDRO DE ARTOLA
Sewer 7/18/2024 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 7/18/2024 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 7/24/2024 Approved ALEJANDRO DE ARTOLA
Verify Rec and Parks Fee Memo 7/24/2024 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 8/7/2024 Approved ALEJANDRO DE ARTOLA
Gas Test 8/29/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 12/12/2024 Approved ALEJANDRO DE ARTOLA
Service/Power Release 12/12/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Final 12/13/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 12/13/2024 Approved ALEJANDRO DE ARTOLA
Final 12/30/2024 OK to Issue CofO ALEJANDRO DE ARTOLA
Green Building Final 12/30/2024 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 12/30/2024 SGSOV Approved ALEJANDRO DE ARTOLA
Service/Power Release 12/30/2024 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 12/30/2024 Approved ALEJANDRO DE ARTOLA