1124 1/2-3/4 W 39TH ST 90037

Certificate Information: 1124 1/2-3/4 W 39TH ST 90037

Application / Permit
22010-10000-00038
Plan Check / Job No.
B22LA00114
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 3-STORY DUPLEX WITH ATTACHED 2-CAR GARAGE (BLDG 5)
Permit Issued
Issued on 9/27/2022
Issuing Office
Metro
Current Status
CofO Issued on 9/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/7/2022 APPLICANT
Assigned to Plan Check Engineer 1/20/2022 JAD BASMA
Corrections Issued 1/28/2022 JAD BASMA
Quality Review Completed 2/2/2022 KEN GILL
Building Plans Picked Up 2/4/2022 APPLICANT
Applicant returned to address corrections 7/26/2022 JAD BASMA
Plan Check Approved 7/28/2022 JAD BASMA
Issued 9/27/2022 APPLICANT
CofO in Progress 8/22/2024 SABAS ALONSO
Permit Finaled 9/10/2024 RUBEN SALAS
CofO Issued 9/10/2024 RUBEN SALAS
Permit Finaled 9/10/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/11/2022 CHRISTOPHER ROCHA
Address approval Cleared 2/16/2022 CHRISTOPHER ROCHA
Address approval Cleared 2/16/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 2/24/2022 CHRISTOPHER ROCHA
Frnt yard landscape/Water mgmt Cleared 3/24/2022 DANIEL CORONADO
Opn space landscape/Water mgmt Cleared 3/24/2022 DANIEL CORONADO
Hydrant and Access approval Cleared 4/15/2022 JOHN CONNEALLY
Highway dedication Cleared 7/7/2022 CHRISTOPHER ROCHA
Low Impact Development Cleared 7/26/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 7/27/2022 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,
Engineer Daba, Geo Consulting Inc; Lic. No.: C24653 15206 GRAYSTONE AVE      NORWALK, CA 90650

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/25/2023 Partial Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 2/15/2023 Approved SABAS ALONSO
Footing/Foundation/Slab 2/15/2023 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 4/3/2023 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/7/2023 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 4/20/2023 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 8/31/2023 Partial Approval SABAS ALONSO
PLUMBING-Rough 9/21/2023 Approved SABAS ALONSO
Shower Pan 9/21/2023 Not Ready for Inspection SABAS ALONSO
Shower Pan 9/25/2023 Approved SABAS ALONSO
HVAC-Rough 9/26/2023 Approved SABAS ALONSO
ELECTRICAL-Rough 10/10/2023 Approved SABAS ALONSO
BUILDING-Rough-Frame 10/17/2023 Approved ENRIQUE MIRELES
Green Building Rough 10/17/2023 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 10/17/2023 Approved ENRIQUE MIRELES
Insulation 11/6/2023 Conditional Approval BRENDAN MORELLI
Insulation 11/13/2023 Approved SABAS ALONSO
Interior/Exterior Lathing 11/13/2023 Partial Approval SABAS ALONSO
Drywall Nailing 11/21/2023 Approved JOSH MEISTER
Interior/Exterior Lathing 12/22/2023 Approved SABAS ALONSO
Underground Mechanical 4/26/2024 Partial Approval SABAS ALONSO
Underground Mechanical 5/6/2024 Approved ALEJANDRO DE ARTOLA
Sewer 5/8/2024 Approved SABAS ALONSO
Underground Mechanical 6/7/2024 Approved JOSH MEISTER
Green Building Final 7/15/2024 Corrections Issued SABAS ALONSO
HVAC-Final 7/15/2024 Corrections Issued SABAS ALONSO
PLUMBING-Final 7/15/2024 Approved SABAS ALONSO
HVAC-Final 7/19/2024 Approved SABAS ALONSO
Final 7/22/2024 Corrections Issued SABAS ALONSO
Green Building Final 7/22/2024 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 7/22/2024 SGSOV Approved SABAS ALONSO
Service/Power Release 7/22/2024 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 7/22/2024 Approved SABAS ALONSO
ELECTRICAL-Final 7/25/2024 Approved SABAS ALONSO
Final 7/25/2024 Corrections Issued SABAS ALONSO
Service/Power Release 7/25/2024 Not Ready for Inspection SABAS ALONSO
Final 8/19/2024 OK to Issue CofO SABAS ALONSO
Service/Power Release 8/19/2024 Not Ready for Inspection SABAS ALONSO