1709 E BENTON WAY 90026
Certificate Information: 1709 E BENTON WAY 90026
- Application / Permit
- 21047-30000-02677
- Plan Check / Job No.
- B21WL05397
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New pool & Spa per std. plan
- Permit Issued
- Issued on 3/20/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/27/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2021 | KHUONG TRUONG |
| Corrections Issued | 12/9/2021 | KHUONG TRUONG |
| Applicant returned to address corrections | 2/8/2022 | EDWIN ESPIN |
| Plan Check Approved | 2/28/2022 | MARJAN SHENASI |
| Building Plans Picked Up | 2/28/2022 | APPLICANT |
| Issued | 3/20/2023 | APPLICANT |
| CofO in Progress | 11/27/2023 | JOAQUIN GREENOUGH |
| Permit Finaled | 12/27/2023 | DEROLD HAUFF |
| CofO Issued | 12/27/2023 | DEROLD HAUFF |
| Permit Finaled | 12/27/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/27/2022 | KHUONG TRUONG |
Contact Information
| Contractor | Emerge Pools Inc; Lic. No.: 1010243-C53 | 14740 VINCENNES STREET PANORAMA CITY, CA 91402 |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 7/19/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Pool Piping | 7/19/2023 | Partial Approval | THOMAS LOGRASSO |
| Pre-Gunite | 7/19/2023 | Approved | THOMAS LOGRASSO |
| Rough-Electrical | 7/19/2023 | Partial Approval | THOMAS LOGRASSO |
| Rough-Plumbing | 7/19/2023 | Partial Approval | THOMAS LOGRASSO |
| Deputy Shotcrete | 7/25/2023 | Conditional Approval | THOMAS LOGRASSO |
| Gas Piping or Gas Test | 7/26/2023 | Approved | THOMAS LOGRASSO |
| Rough-Electrical | 7/26/2023 | Approved | THOMAS LOGRASSO |
| Enclosure/Fence | 9/6/2023 | Partial Inspection | THOMAS LOGRASSO |
| Enclosure/Fence | 10/26/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Grounding or Bonding | 10/26/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Enclosure/Fence | 10/30/2023 | Approved | THOMAS LOGRASSO |
| Pool Equipment Noise Test | 11/7/2023 | Approved | ANDEY CHAPARRO |
| Excavation/Setback/Form/Re-Bar | 11/8/2023 | Approved | THOMAS LOGRASSO |
| Final | 11/8/2023 | Corrections Issued | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 11/8/2023 | SGSOV Approved | THOMAS LOGRASSO |
| Final | 11/22/2023 | OK to Issue CofO | JOAQUIN GREENOUGH |