8032 S EL MANOR AVE 90045
Certificate Information: 8032 S EL MANOR AVE 90045
- Application / Permit
- 21047-30000-02292
- Plan Check / Job No.
- B21WL04548
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- Swimming pool and spa with concrete accent wall & water spouts, new raised wood deck per engineer's design.
- Permit Issued
- Issued on 2/4/2022
- Issuing Office
- Current Status
- CofO Issued on 7/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2021 | KHUONG TRUONG |
| Corrections Issued | 10/30/2021 | KHUONG TRUONG |
| Plan Check Approved | 1/25/2022 | KHUONG TRUONG |
| Issued | 2/4/2022 | APPLICANT |
| Building Plans Picked Up | 2/11/2022 | APPLICANT |
| CofO in Progress | 7/26/2022 | RICHARD STEINBACH |
| CofO Issued | 7/28/2022 | DANIEL ORRANTE |
| Permit Finaled | 7/28/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/5/2022 | WALTER RAMIREZ |
Contact Information
| Contractor | Chadwick & Doggett General Contracting Inc; Lic. No.: 756093-B | 13428 MAXELLA AVENUE MARINA DEL REY, CA 90292 |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 2999 OVERLAND AVE STE 103 LOS ANGELES, CA 90064 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/22/2022 | Approved | BOBBY KEY |
| Grounding or Bonding | 3/22/2022 | Approved | BOBBY KEY |
| Pool Piping | 3/22/2022 | Approved | BOBBY KEY |
| Pre-Gunite | 3/22/2022 | Approved | BOBBY KEY |
| Rough-Electrical | 3/22/2022 | Approved | BOBBY KEY |
| Deputy Shotcrete | 3/23/2022 | No Access for Inspection | RICHARD STEINBACH |
| Deputy Shotcrete | 4/1/2022 | Conditional Approval | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 4/14/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 4/29/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Pool Equipment Noise Test | 6/29/2022 | Not Ready for Inspection | AGUSTIN ALVAREZMORALES |
| Pool Equipment Noise Test | 6/30/2022 | Not Ready for Inspection | AGUSTIN ALVAREZMORALES |
| Equipment Noise Level | 7/1/2022 | Not Ready for Inspection | JAMES VORHIS |
| SGSOV-Seismic Gas S/O Valve | 7/1/2022 | SGSOV Not Ready | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 7/18/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 7/18/2022 | Corrections Issued | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 7/18/2022 | SGSOV Approved | JESUS RODRIGUEZ |
| Equipment Noise Level | 7/19/2022 | Approved | JAMES VORHIS |
| Excavation/Setback/Form/Re-Bar | 7/21/2022 | Corrections Issued | EVAN COOPER |
| Final | 7/21/2022 | Not Ready for Inspection | EVAN COOPER |
| Enclosure/Fence | 7/26/2022 | Approved | RICHARD STEINBACH |
| Excavation/Setback/Form/Re-Bar | 7/26/2022 | Approved | RICHARD STEINBACH |
| Final | 7/26/2022 | OK to Issue CofO | RICHARD STEINBACH |