1635 N BLUE JAY WAY 90069
Certificate Information: 1635 N BLUE JAY WAY 90069
- Application / Permit
- 21047-30000-02278
- Plan Check / Job No.
- B21WL04513
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New swimming pool (14'-10" W x 69'-5" L - 3'-6" deep)
- Permit Issued
- Issued on 8/18/2022
- Issuing Office
- Metro
- Current Status
- Issued on 8/18/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2021 | REZA HAGHIGHAT |
| Corrections Issued | 10/31/2021 | REZA HAGHIGHAT |
| Quality Review Completed | 11/8/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 12/22/2021 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 5/13/2022 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 5/30/2022 | REZA HAGHIGHAT |
| Building Plans Picked Up | 6/2/2022 | APPLICANT |
| Plan Check Approved | 8/15/2022 | REZA HAGHIGHAT |
| Issued | 8/18/2022 | APPLICANT |
Permit Application Clearance Information
| ZA Case | Cleared | 2/25/2022 | RYAN LY |
| Excavation more than 5-ft deep | Cleared | 5/31/2022 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 5/31/2022 | REZA HAGHIGHAT |
Contact Information
| Architect | Schneider,, Thomas Patrick; Lic. No.: C29963 | 11828 W PICO BLVD LOS ANGELES, CA 90064 |
| Contractor | Pillar Building Group Llc; Lic. No.: 1017041-B | 8109 ORION AVE VAN NUYS, CA 91406 |
| Engineer | , ; Lic. No.: C93123 | 889 PIERCE COURT, SUITE 101 THOUSAND OAKS, CA 91360 |
| Engineer | Behshid,, Farshid; Lic. No.: S4585 | 10866 WIMER COUNTRY ROAD SUNLAND, CA 91040 |
| Engineer | Daneshfar,, Kourosh Dan; Lic. No.: C68377 | 19722 ARMINTA ST WINNETKA, CA 91306 |
| Geologist | Feffer,, Joshua Rafael; Lic. No.: EG2138 | 12253 GORHAM AVE LOS ANGELES, CA 90049 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/26/2024 | Conditional Approval | RAUL BARAJAS |
| Pre-Inspection | 9/19/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 9/20/2024 | Partial Approval | RAUL BARAJAS |
| Grounding or Bonding | 9/20/2024 | Approved | RAUL BARAJAS |
| Pre-Gunite | 9/20/2024 | Approved | RAUL BARAJAS |
| Deputy Shotcrete | 9/25/2024 | Conditional Approval | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 4/14/2025 | Conditional Approval | ROY SPAULDING |
| Excavation/Setback/Form/Re-Bar | 8/14/2025 | Approved | BRENDAN MORELLI |
| Grounding or Bonding | 8/14/2025 | Partial Approval | BRENDAN MORELLI |
| Pool Piping | 8/14/2025 | Approved | BRENDAN MORELLI |
| Deputy Shotcrete | 10/8/2025 | Conditional Approval | ROY SPAULDING |