2420 S DUXBURY PL 90034

Certificate Information: 2420 S DUXBURY PL 90034

Application / Permit
21047-30000-02119
Plan Check / Job No.
B21WL04244
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
New Pool & SPA per Standard Plan 268
Permit Issued
Issued on 6/14/2022
Issuing Office
Current Status
CofO Issued on 8/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/23/2021 APPLICANT
Assigned to Plan Check Engineer 10/7/2021 DAVID CASTILLO
Corrections Issued 10/15/2021 DAVID CASTILLO
Quality Review Completed 10/27/2021 TARIK SAOUD
Plan Check Approved 5/17/2022 DAVID CASTILLO
Issued 6/14/2022 APPLICANT
Building Plans Picked Up 6/14/2022 APPLICANT
Permit Finaled 8/6/2024 DANIEL ORRANTE
CofO Issued 8/6/2024 DANIEL ORRANTE
Permit Finaled 8/6/2024 DANIEL ORRANTE

Permit Application Clearance Information

Excavation more than 5-ft deep Cleared 1/26/2022 CALOSHA APPROVED
Construction within easement Cleared 5/9/2022 WALTER RAMIREZ
Grading Pre-Inspection Cleared 5/17/2022 DAVID CASTILLO

Contact Information

Architect Tomaro,, Louie Mark; Lic. No.: C22941 2617 N SEPULVEDA BLVD SUITE 100      MANHATTAN BEACH, CA 90266
Contractor Drexel Construction Management Llc; Lic. No.: 1014160-B 5168 W PICO BLVD      LOS ANGELES, CA 90019
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807
Engineer Messiha,, Hany Gamil; Lic. No.: C56766 19648 MULBERRY DR      WALNUT, CA 91789
Engineer Tucker,, Keith D; Lic. No.: GE841 PO BOX 8133      HUNTINGTON BEACH, CA 92615

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 11/27/2023 Corrections Issued OGANES TARAKHCHYAN
Rough-Electrical 11/27/2023 Approved OGANES TARAKHCHYAN
Rough-Plumbing 11/27/2023 Approved OGANES TARAKHCHYAN
Gunite 11/29/2023 Approved OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 12/4/2023 Approved OGANES TARAKHCHYAN
Pre-Gunite 12/4/2023 Approved OGANES TARAKHCHYAN
Deputy Shotcrete 12/18/2023 Conditional Approval MICHAEL PELHAM
Enclosure/Fence 5/8/2024 Approved OGANES TARAKHCHYAN
Final 7/10/2024 Corrections Issued ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 7/10/2024 SGSOV Not Ready ASHLEY THOMPSON
Enclosure/Fence 7/12/2024 Approved ASHLEY THOMPSON
Final 7/12/2024 Conditional Approval ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 7/12/2024 SGSOV Approved ASHLEY THOMPSON