139 N SALTAIR AVE 90049
Certificate Information: 139 N SALTAIR AVE 90049
- Application / Permit
- 21047-30000-02070
- Plan Check / Job No.
- B21WL04138
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- new pool & spa per std. plan #268
- Permit Issued
- Issued on 10/14/2021
- Issuing Office
- Current Status
- CofO Issued on 2/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/20/2021 | KHUONG TRUONG |
| Corrections Issued | 9/20/2021 | KHUONG TRUONG |
| Plan Check Approved | 10/5/2021 | ALFREDO JARA |
| Issued | 10/14/2021 | APPLICANT |
| CofO in Progress | 2/8/2025 | MICHAEL PELHAM |
| Permit Finaled | 2/20/2025 | RICHARD STEINBACH |
| CofO Issued | 2/20/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/20/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/5/2021 | ALFREDO JARA |
Contact Information
| Contractor | Zion Pools; Lic. No.: 902972-C53 | 4020 WILLIAMS AVE CLAREMONT, CA 91711 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/27/2022 | Approved | CARLOS MATAMOROS |
| Grounding or Bonding | 12/27/2022 | Approved | CARLOS MATAMOROS |
| Pool Piping | 12/27/2022 | Partial Approval | CARLOS MATAMOROS |
| Pre-Gunite | 12/27/2022 | Approved | CARLOS MATAMOROS |
| Rough-Electrical | 12/27/2022 | Partial Approval | CARLOS MATAMOROS |
| Rough-Plumbing | 12/27/2022 | Approved | CARLOS MATAMOROS |
| Deputy Shotcrete | 1/6/2023 | Conditional Approval | MICHAEL PELHAM |
| Pool Piping | 5/18/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Rough-Electrical | 5/18/2023 | Approved | CARLOS MATAMOROS |
| Rough-Electrical | 5/24/2023 | Approved | CARLOS MATAMOROS |
| Rough-Plumbing | 5/24/2023 | Approved | CARLOS MATAMOROS |
| Deck | 1/17/2024 | Approved | CARLOS MATAMOROS |
| Grounding or Bonding | 1/17/2024 | Approved | CARLOS MATAMOROS |
| Enclosure/Fence | 7/25/2024 | Corrections Issued | CARLOS MATAMOROS |
| Enclosure/Fence | 8/7/2024 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 10/29/2024 | Corrections Issued | CARLOS MATAMOROS |
| Final | 10/29/2024 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Final | 10/29/2024 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 10/29/2024 | SGSOV Not Ready | CARLOS MATAMOROS |
| ELECTRICAL-Final | 11/4/2024 | Approved | CARLOS MATAMOROS |
| Final | 11/4/2024 | Corrections Issued | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 11/4/2024 | SGSOV Approved | CARLOS MATAMOROS |
| Final | 2/8/2025 | OK to Issue CofO | MICHAEL PELHAM |