305 S ANITA AVE 90049

Certificate Information: 305 S ANITA AVE 90049

Application / Permit
21047-30000-02060
Plan Check / Job No.
B21WL04109
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(N) Pool and Spa per Standard Plan #268
Permit Issued
Issued on 10/13/2022
Issuing Office
Current Status
CofO Issued on 4/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/17/2021 APPLICANT
Assigned to Plan Check Engineer 9/21/2021 MANUEL GARCIA
Corrections Issued 9/21/2021 MANUEL GARCIA
Applicant returned to address corrections 12/14/2021 MARJAN SHENASI
Applicant returned to address corrections 5/21/2022 JASON JANGADA
Applicant returned to address corrections 7/15/2022 DAVID CASTILLO
Applicant returned to address corrections 8/10/2022 EDWIN ESPIN
Applicant returned to address corrections 8/31/2022 JASON JANGADA
Plan Check Approved 10/12/2022 EDWIN ESPIN
Issued 10/13/2022 APPLICANT
Building Plans Picked Up 11/9/2022 APPLICANT
CofO in Progress 4/25/2023 KEVIN SARGSYAN
Permit Finaled 4/26/2023 DANIEL ORRANTE
CofO Issued 4/26/2023 DANIEL ORRANTE
Permit Finaled 4/26/2023 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 5/20/2022 MANUEL GARCIA

Contact Information

Contractor Castle Rock Designs Inc; Lic. No.: 925052-B 8023 BEVERLY BLVD SUITE 1-110      LOS ANGELES, CA 90048
Engineer Eftekhari,, Hossein; Lic. No.: C50121 5945 SETTLER COURT      ANAHEIM, CA 92807
Engineer Yadegari,, Shahriar; Lic. No.: C64591 10301 KESWICK AVE      LOS ANGELES, CA 90064

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 10/21/2022 Not Ready for Inspection KEVIN SARGSYAN
Pool Piping 10/21/2022 Not Ready for Inspection KEVIN SARGSYAN
Pre-Gunite 10/21/2022 Not Ready for Inspection KEVIN SARGSYAN
Rough-Electrical 10/21/2022 Not Ready for Inspection KEVIN SARGSYAN
Rough-Plumbing 10/21/2022 Not Ready for Inspection KEVIN SARGSYAN
Pre-Gunite 10/24/2022 Corrections Issued KEVIN SARGSYAN
Gas Piping or Gas Test 10/26/2022 Approved KEVIN SARGSYAN
Pool Piping 10/26/2022 Approved KEVIN SARGSYAN
Pre-Gunite 10/26/2022 Conditional Approval KEVIN SARGSYAN
Rough-Electrical 10/26/2022 Approved KEVIN SARGSYAN
Deputy Shotcrete 10/27/2022 Conditional Approval KEVIN SARGSYAN
Grounding or Bonding 2/17/2023 Approved OGANES TARAKHCHYAN
Enclosure/Fence 2/27/2023 Corrections Issued CARLOS MATAMOROS
Enclosure/Fence 3/1/2023 Approved OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 3/31/2023 Approved CARLOS MATAMOROS
Final 3/31/2023 Corrections Issued CARLOS MATAMOROS
Pool Equipment Noise Test 3/31/2023 Approved AGUSTIN ALVAREZMORALES
Pool/Spa Cover 3/31/2023 Not Ready for Inspection CARLOS MATAMOROS
Pre-Gunite 3/31/2023 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 3/31/2023 SGSOV Not Ready CARLOS MATAMOROS
Final 4/13/2023 Corrections Issued OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 4/13/2023 SGSOV Approved OGANES TARAKHCHYAN
Final 4/25/2023 OK to Issue CofO KEVIN SARGSYAN