636 N WALTHER WAY 90049
Certificate Information: 636 N WALTHER WAY 90049
- Application / Permit
- 21047-30000-02043
- Plan Check / Job No.
- B21WL04038
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- new pool *** 2 of 4 ***
- Permit Issued
- Issued on 10/25/2022
- Issuing Office
- Current Status
- CofO Issued on 4/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2021 | FELIPE HERNANDEZ |
| Corrections Issued | 10/6/2021 | FELIPE HERNANDEZ |
| Quality Review Completed | 10/18/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 7/6/2022 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 8/10/2022 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 8/16/2022 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 9/6/2022 | CHIHARU SUZUKI |
| Plan Check Approved | 10/17/2022 | CHIHARU SUZUKI |
| Issued | 10/25/2022 | APPLICANT |
| Building Plans Picked Up | 10/26/2022 | APPLICANT |
| CofO in Progress | 4/7/2025 | KEVIN SARGSYAN |
| Permit Finaled | 4/24/2025 | RICHARD STEINBACH |
| CofO Issued | 4/24/2025 | RICHARD STEINBACH |
| Permit Finaled | 4/24/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 8/10/2022 | FELIPE HERNANDEZ |
| Grading Pre-Inspection | Cleared | 8/10/2022 | FELIPE HERNANDEZ |
Contact Information
| Architect | Schoeplein,, Marc; Lic. No.: C24842 | 960 BLUEGRASS WAY LOS ANGELES, CA 90049 |
| Contractor | Basix Designs & Remodeling Inc; Lic. No.: 769443-B | 650 S HIGHLAND AVE LOS ANGELES, CA 90036 |
| Engineer | Garza,, Omar Leonel; Lic. No.: S5593 | 600 WILSHIRE BLVD 760 LOS ANGELES, CA 90017 |
| Engineer | Lund,, Tracy Stephen; Lic. No.: C52531 | 511 W GRAND AVE EL SEGUNDO, CA 90245 |
| Engineer | Mahn,, Jonathan Edward; Lic. No.: C60293 | 12848 FOOTHILL BLVD SYLMAR, CA 91381 |
| Geologist | Triebold,, Mark John; Lic. No.: EG1796 | 6906 QUITO COURT CAMARILLO, CA 93012 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 7/26/2023 | Not Ready for Inspection | KENNETH NAGLE |
| Piling/Pier/Caisson | 7/27/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Deputy Other (see comments) | 7/31/2023 | No Access for Inspection | KENNETH NAGLE |
| Piling/Pier/Caisson | 7/31/2023 | Partial Approval | KEVIN SARGSYAN |
| Piling/Pier/Caisson | 8/16/2023 | Partial Approval | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 9/20/2023 | Corrections Issued | KENNETH NAGLE |
| Pool Piping | 9/20/2023 | Corrections Issued | KENNETH NAGLE |
| Pre-Gunite | 9/20/2023 | Corrections Issued | KENNETH NAGLE |
| Grounding or Bonding | 9/22/2023 | Partial Approval | ARAM AVEDISIAN |
| Pool Piping | 9/22/2023 | Approved | ARAM AVEDISIAN |
| Pre-Gunite | 9/22/2023 | Approved | ARAM AVEDISIAN |
| Deputy Shotcrete | 9/26/2023 | Approved | ARAM AVEDISIAN |
| Deck | 12/5/2023 | Approved | KEVIN SARGSYAN |
| Grounding or Bonding | 12/5/2023 | Approved | KEVIN SARGSYAN |
| Gas Piping or Gas Test | 2/1/2024 | Approved | KEVIN SARGSYAN |
| Enclosure/Fence | 6/7/2024 | Corrections Issued | KEVIN SARGSYAN |
| Enclosure/Fence | 6/14/2024 | Approved | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 3/4/2025 | Approved | KEVIN SARGSYAN |
| Final | 3/4/2025 | Corrections Issued | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 3/4/2025 | SGSOV Approved | KEVIN SARGSYAN |
| Final | 4/3/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| Final | 4/7/2025 | OK to Issue CofO | KEVIN SARGSYAN |