5988 W 76TH ST 90045
Certificate Information: 5988 W 76TH ST 90045
- Application / Permit
- 21047-30000-01960
- Plan Check / Job No.
- B21WL03820
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N)Pool & SPA. Per standard plans# 270
- Permit Issued
- Issued on 11/12/2021
- Issuing Office
- Current Status
- CofO Issued on 7/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/30/2021 | MANUEL GARCIA |
| Corrections Issued | 8/30/2021 | MANUEL GARCIA |
| Plan Check Approved | 11/7/2021 | ALFREDO JARA |
| Issued | 11/12/2021 | APPLICANT |
| Building Plans Picked Up | 11/15/2021 | APPLICANT |
| CofO in Progress | 6/28/2024 | BOBBY KEY |
| Permit Finaled | 7/6/2024 | DANIEL ORRANTE |
| CofO Issued | 7/6/2024 | DANIEL ORRANTE |
| Permit Finaled | 7/6/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZA Case | Cleared | 9/20/2021 | PABLO ESTRADA |
| Grading Pre-Inspection | Cleared | 11/7/2021 | MANUEL GARCIA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/19/2021 | Approved | ENRIQUE MIRELES |
| Gas Piping or Gas Test | 2/2/2022 | Conditional Approval | DAVID FEILER |
| Pool Piping | 2/2/2022 | Conditional Approval | DAVID FEILER |
| Pre-Gunite | 2/2/2022 | Corrections Issued | DAVID FEILER |
| Rough-Electrical | 2/2/2022 | Conditional Approval | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 2/7/2022 | Not Ready for Inspection | ANDREW NAVE |
| Gas Piping or Gas Test | 2/7/2022 | Not Ready for Inspection | ANDREW NAVE |
| Grading Pre-Inspection | 2/7/2022 | Not Ready for Inspection | ANDREW NAVE |
| Grounding or Bonding | 2/7/2022 | Not Ready for Inspection | ANDREW NAVE |
| Pre-Gunite | 2/7/2022 | Corrections Issued | ANDREW NAVE |
| Rough-Electrical | 2/7/2022 | Not Ready for Inspection | ANDREW NAVE |
| Rough-Plumbing | 2/7/2022 | Not Ready for Inspection | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 2/16/2022 | Partial Inspection | DAVID FEILER |
| Grounding or Bonding | 2/16/2022 | Partial Inspection | DAVID FEILER |
| Pool Piping | 2/16/2022 | Partial Inspection | DAVID FEILER |
| Pre-Gunite | 2/16/2022 | Corrections Issued | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 2/22/2022 | Approved | BOBBY KEY |
| Grounding or Bonding | 2/22/2022 | Approved | BOBBY KEY |
| Pool Piping | 2/22/2022 | Approved | BOBBY KEY |
| Pre-Gunite | 2/22/2022 | Approved | BOBBY KEY |
| Deputy Shotcrete | 3/3/2022 | Conditional Approval | BOBBY KEY |
| Enclosure/Fence | 4/5/2023 | Corrections Issued | BOBBY KEY |
| Pool/Spa Cover | 4/5/2023 | Not Ready for Inspection | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 4/5/2023 | SGSOV Approved | BOBBY KEY |
| Enclosure/Fence | 12/1/2023 | Not Ready for Inspection | BOBBY KEY |
| Final | 12/1/2023 | Not Ready for Inspection | BOBBY KEY |
| Pool Equipment Noise Test | 12/5/2023 | Approved | JAMES VORHIS |
| Final | 5/20/2024 | Corrections Issued | BOBBY KEY |
| Final | 6/26/2024 | Corrections Issued | BOBBY KEY |
| Final | 6/28/2024 | OK to Issue CofO | BOBBY KEY |