5988 W 76TH ST 90045

Certificate Information: 5988 W 76TH ST 90045

Application / Permit
21047-30000-01960
Plan Check / Job No.
B21WL03820
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(N)Pool & SPA. Per standard plans# 270
Permit Issued
Issued on 11/12/2021
Issuing Office
Current Status
CofO Issued on 7/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/27/2021 APPLICANT
Assigned to Plan Check Engineer 8/30/2021 MANUEL GARCIA
Corrections Issued 8/30/2021 MANUEL GARCIA
Plan Check Approved 11/7/2021 ALFREDO JARA
Issued 11/12/2021 APPLICANT
Building Plans Picked Up 11/15/2021 APPLICANT
CofO in Progress 6/28/2024 BOBBY KEY
Permit Finaled 7/6/2024 DANIEL ORRANTE
CofO Issued 7/6/2024 DANIEL ORRANTE
Permit Finaled 7/6/2024 DANIEL ORRANTE

Permit Application Clearance Information

ZA Case Cleared 9/20/2021 PABLO ESTRADA
Grading Pre-Inspection Cleared 11/7/2021 MANUEL GARCIA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/19/2021 Approved ENRIQUE MIRELES
Gas Piping or Gas Test 2/2/2022 Conditional Approval DAVID FEILER
Pool Piping 2/2/2022 Conditional Approval DAVID FEILER
Pre-Gunite 2/2/2022 Corrections Issued DAVID FEILER
Rough-Electrical 2/2/2022 Conditional Approval DAVID FEILER
Excavation/Setback/Form/Re-Bar 2/7/2022 Not Ready for Inspection ANDREW NAVE
Gas Piping or Gas Test 2/7/2022 Not Ready for Inspection ANDREW NAVE
Grading Pre-Inspection 2/7/2022 Not Ready for Inspection ANDREW NAVE
Grounding or Bonding 2/7/2022 Not Ready for Inspection ANDREW NAVE
Pre-Gunite 2/7/2022 Corrections Issued ANDREW NAVE
Rough-Electrical 2/7/2022 Not Ready for Inspection ANDREW NAVE
Rough-Plumbing 2/7/2022 Not Ready for Inspection ANDREW NAVE
Excavation/Setback/Form/Re-Bar 2/16/2022 Partial Inspection DAVID FEILER
Grounding or Bonding 2/16/2022 Partial Inspection DAVID FEILER
Pool Piping 2/16/2022 Partial Inspection DAVID FEILER
Pre-Gunite 2/16/2022 Corrections Issued DAVID FEILER
Excavation/Setback/Form/Re-Bar 2/22/2022 Approved BOBBY KEY
Grounding or Bonding 2/22/2022 Approved BOBBY KEY
Pool Piping 2/22/2022 Approved BOBBY KEY
Pre-Gunite 2/22/2022 Approved BOBBY KEY
Deputy Shotcrete 3/3/2022 Conditional Approval BOBBY KEY
Enclosure/Fence 4/5/2023 Corrections Issued BOBBY KEY
Pool/Spa Cover 4/5/2023 Not Ready for Inspection BOBBY KEY
SGSOV-Seismic Gas S/O Valve 4/5/2023 SGSOV Approved BOBBY KEY
Enclosure/Fence 12/1/2023 Not Ready for Inspection BOBBY KEY
Final 12/1/2023 Not Ready for Inspection BOBBY KEY
Pool Equipment Noise Test 12/5/2023 Approved JAMES VORHIS
Final 5/20/2024 Corrections Issued BOBBY KEY
Final 6/26/2024 Corrections Issued BOBBY KEY
Final 6/28/2024 OK to Issue CofO BOBBY KEY