9450 W SIERRA MAR DR 90069

Certificate Information: 9450 W SIERRA MAR DR 90069

Application / Permit
21047-30000-01924
Plan Check / Job No.
B21WL03762
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
New pool/spa and deck. New louver attached to (e) front elevation *** 2 of 2 ***
Permit Issued
Issued on 7/18/2022
Issuing Office
Current Status
Issued on 7/18/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/24/2021 APPLICANT
Assigned to Plan Check Engineer 9/9/2021 RICHARD GARCIA
Corrections Issued 9/12/2021 RICHARD GARCIA
Quality Review Completed 9/23/2021 TARIK SAOUD
Applicant returned to address corrections 2/22/2022 RICHARD GARCIA
Applicant returned to address corrections 3/3/2022 RICHARD GARCIA
Building Plans Picked Up 3/7/2022 APPLICANT
Plan Check Approved 5/26/2022 RICHARD GARCIA
Issued 7/18/2022 APPLICANT

Permit Application Clearance Information

ZA Case Cleared 11/29/2021 RUBEN VASQUEZ
Eng Process Fee Ord 176,300 Cleared 1/3/2022 STEVE MELGAR
Work Adjacent to Public Way Cleared 1/11/2022 ARMEN SARKISIAN
Grading Pre-Inspection Cleared 3/3/2022 RICHARD GARCIA

Contact Information

Contractor Noesis Builders Inc; Lic. No.: 1046562-B 8383 WILSHIRE BOULEVARD SUITE   740    BEVERLY HILLS, CA 90211
Engineer Messiha,, Hany Gamil; Lic. No.: C56766 19648 MULBERRY DR      WALNUT, CA 91789

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/6/2022 Partial Inspection RAUL BARAJAS
Piling/Pier/Caisson 12/5/2022 Corrections Issued RAUL BARAJAS
Solar System 12/5/2022 Not Ready for Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 12/7/2022 Partial Approval RAUL BARAJAS
Pre-Inspection 12/7/2022 Approved RAUL BARAJAS
Piling/Pier/Caisson 12/29/2022 Not Ready for Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 1/26/2023 Corrections Issued RAUL BARAJAS
Piling/Pier/Caisson 1/26/2023 Corrections Issued RAUL BARAJAS
Deputy Other (see comments) 1/30/2023 Approved RAUL BARAJAS
Piling/Pier/Caisson 1/30/2023 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 3/9/2023 Partial Approval RAUL BARAJAS
Pre-Inspection 3/9/2023 Partial Approval RAUL BARAJAS
Solar System 3/9/2023 Not Ready for Inspection RAUL BARAJAS
Deputy Other (see comments) 3/10/2023 Conditional Approval RAUL BARAJAS
Piling/Pier/Caisson 3/16/2023 Not Ready for Inspection RAUL BARAJAS
Piling/Pier/Caisson 5/17/2023 Corrections Issued RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 5/31/2023 Corrections Issued RAUL BARAJAS
Piling/Pier/Caisson 5/31/2023 Not Ready for Inspection RAUL BARAJAS
Piling/Pier/Caisson 7/17/2023 Partial Approval RAUL BARAJAS
Deputy Other (see comments) 8/2/2023 Conditional Approval RAUL BARAJAS
Piling/Pier/Caisson 8/4/2023 Partial Approval RAUL BARAJAS
Deputy Other (see comments) 8/30/2023 Conditional Approval RAUL BARAJAS