2630 N ALGODON CT 90046

Certificate Information: 2630 N ALGODON CT 90046

Application / Permit
21047-30000-01809
Plan Check / Job No.
B21WL03587
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW POOL AND SPA
Permit Issued
Issued on 4/7/2022
Issuing Office
Current Status
CofO Issued on 5/14/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/10/2021 APPLICANT
Assigned to Plan Check Engineer 9/16/2021 VLADIMIR ARUTYUNYAN
Corrections Issued 9/21/2021 VLADIMIR ARUTYUNYAN
Quality Review Completed 10/7/2021 TARIK SAOUD
Applicant returned to address corrections 12/13/2021 VLADIMIR ARUTYUNYAN
Building Plans Picked Up 12/16/2021 APPLICANT
Plan Check Approved 3/16/2022 SERGIO SILVA
Issued 4/7/2022 APPLICANT
CofO in Progress 5/5/2026 ROY SPAULDING
Permit Finaled 5/14/2026 DEROLD HAUFF
CofO Issued 5/14/2026 DEROLD HAUFF
Permit Finaled 5/14/2026 DEROLD HAUFF

Permit Application Clearance Information

Specific Plan Cleared 11/5/2021 DENZEL HENDERSON
ZA Case Cleared 11/5/2021 DENZEL HENDERSON

Contact Information

Contractor Owner-Builder       ,
Engineer Eftekhari,, Hossein; Lic. No.: C50121 5945 SETTLER COURT      ANAHEIM, CA 92807
Engineer Tuchscher,, James Todd; Lic. No.: C77649 5503 E 2ND ST      LONG BEACH, CA 90803

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/12/2022 Approved RAUL BARAJAS
Deputy Shotcrete 1/23/2023 Conditional Approval STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 1/25/2023 Approved STUART CHAPMAN
Grounding or Bonding 9/22/2025 Approved ROY SPAULDING
Pool Piping 4/9/2026 Approved ROY SPAULDING
Enclosure/Fence 4/23/2026 Corrections Issued ROY SPAULDING
Pre-Gunite 4/23/2026 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 4/23/2026 SGSOV Not Ready ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 4/29/2026 SGSOV Not Ready ROY SPAULDING
Enclosure/Fence 4/30/2026 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 4/30/2026 SGSOV Not Ready ROY SPAULDING
Enclosure/Fence 5/1/2026 Approved ROY SPAULDING
Final 5/4/2026 OK to Issue CofO ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 5/4/2026 SGSOV Approved ROY SPAULDING