3207 S THATCHER AVE 90292
Certificate Information: 3207 S THATCHER AVE 90292
- Application / Permit
- 21047-30000-01777
- Plan Check / Job No.
- B21WL03532
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) pool 11'-0 X 22'-4" with spa and baja shelf inside the pool per Standard Plan # 254 at rear of the lot.
- Permit Issued
- Issued on 8/31/2022
- Issuing Office
- Current Status
- Issued on 8/31/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/9/2021 | SERGIO SILVA |
| Corrections Issued | 8/10/2021 | SERGIO SILVA |
| Applicant returned to address corrections | 9/16/2021 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 11/18/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 12/21/2021 | ALFREDO JARA |
| Applicant returned to address corrections | 7/27/2022 | EDWIN ESPIN |
| Applicant returned to address corrections | 8/15/2022 | EDWIN ESPIN |
| Applicant returned to address corrections | 8/29/2022 | ALFREDO JARA |
| Plan Check Approved | 8/31/2022 | ALFREDO JARA |
| Issued | 8/31/2022 | APPLICANT |
| Building Plans Picked Up | 9/8/2022 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 4/8/2022 | RIDWAN HARDY |
| Coastal Zone | Cleared | 6/15/2022 | YINGSHI HUANG |
| Miscellaneous | Cleared | 6/15/2022 | YINGSHI HUANG |
| Specific Plan | Cleared | 7/12/2022 | IRA BROWN |
| Specific Plan | Cleared | 7/12/2022 | IRA BROWN |
| Miscellaneous | Cleared | 7/14/2022 | YINGSHI HUANG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Azizisefat,, Solayman; Lic. No.: C57840 | 19510 VENTURA BLVD STE 110 TARZANA, CA 91356 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/16/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Pre-Gunite | 9/16/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Deputy Shotcrete | 10/5/2022 | Approved | JESUS RODRIGUEZ |
| Deck | 10/20/2022 | Approved | ANDREW NAVE |
| Grounding or Bonding | 10/20/2022 | Approved | ANDREW NAVE |
| ELECTRICAL-Final | 11/3/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Enclosure/Fence | 11/3/2022 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Final | 11/3/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |