15507 W EARLHAM ST 90272

Certificate Information: 15507 W EARLHAM ST 90272

Application / Permit
21047-30000-01764
Plan Check / Job No.
B21WL03495
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
backyard swimming pool per city std. plan #270 *** 1 of 2 ***
Permit Issued
Issued on 8/29/2022
Issuing Office
Metro
Current Status
CofO Issued on 8/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/4/2021 APPLICANT
Assigned to Plan Check Engineer 8/5/2021 KHUONG TRUONG
Corrections Issued 8/5/2021 KHUONG TRUONG
Applicant returned to address corrections 10/26/2021 ALFREDO JARA
Applicant returned to address corrections 8/10/2022 AUNG SOE
Plan Check Approved 8/29/2022 DANIEL SANJUAN
Issued 8/29/2022 APPLICANT
CofO in Progress 8/26/2024 EVAN COOPER
Permit Finaled 8/30/2024 RICHARD STEINBACH
CofO Issued 8/30/2024 RICHARD STEINBACH
Permit Finaled 8/30/2024 RICHARD STEINBACH

Permit Application Clearance Information

Coastal Zone Cleared 3/7/2022 RICHARD REASER
ZI Cleared 3/7/2022 RICHARD REASER
Construction near power lines Cleared 6/15/2022 RIDWAN HARDY

Contact Information

Contractor Marino Pool And Spa; Lic. No.: 528696-C53 5739 KANAN RD 364      AGOURA HILLS, CA 91301
Engineer Cristescu,, Barbu Dan; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 9/23/2022 Approved ANDREW NAVE
Deputy Shotcrete 9/26/2022 Conditional Approval BRENDAN LOONEY
Deck 10/17/2022 Partial Approval CHRISTOPHER WILSON
Final 10/17/2022 Corrections Issued CHRISTOPHER WILSON
Grounding or Bonding 10/20/2022 Partial Approval JUAN VALENZUELA
Enclosure/Fence 2/6/2023 Approved BRENDAN LOONEY
Final 12/11/2023 Corrections Issued EVAN COOPER
SGSOV-Seismic Gas S/O Valve 12/11/2023 SGSOV Not Ready EVAN COOPER
Equipment Noise Level 12/28/2023 Approved JAMES VORHIS
Final 3/27/2024 Corrections Issued KENNETH NAGLE
SGSOV-Seismic Gas S/O Valve 3/27/2024 SGSOV Approved KENNETH NAGLE
Final 5/22/2024 Corrections Issued EVAN COOPER
Final 8/26/2024 OK to Issue CofO EVAN COOPER