16838 W OAK VIEW DR 91436
Certificate Information: 16838 W OAK VIEW DR 91436
- Application / Permit
- 21047-30000-01528
- Plan Check / Job No.
- B21WL02904
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) swimming pool and SPA. Per engineering design.
- Permit Issued
- Issued on 2/23/2024
- Issuing Office
- Valley
- Current Status
- Issued on 2/23/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2021 | ALFREDO JARA |
| Corrections Issued | 7/27/2021 | ALFREDO JARA |
| Quality Review Completed | 8/17/2021 | TARIK SAOUD |
| Building Plans Picked Up | 8/18/2021 | APPLICANT |
| Applicant returned to address corrections | 9/7/2022 | ALFREDO JARA |
| Applicant returned to address corrections | 11/17/2022 | ALFREDO JARA |
| Applicant returned to address corrections | 2/13/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 5/16/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 5/23/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 8/28/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 1/3/2024 | SERGIO SILVA |
| Plan Check Approved | 1/3/2024 | SERGIO SILVA |
| No Progress | 1/3/2024 | SERGIO SILVA |
| Plan Check Approved | 1/3/2024 | SERGIO SILVA |
| Issued | 2/23/2024 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/15/2023 | ALFREDO JARA |
Contact Information
| Contractor | Val Vista Builders Llc; Lic. No.: 1116703-B | 3600 HARBOR BL STE 110 PMB 336 OXNARD, CA 93035 |
| Engineer | Ilasin,, John Lacebal; Lic. No.: C67469 | 1011 OARFISH LN OXNARD, CA 93035 |
| Engineer | Poffenbarger,, Kevin Lawrence; Lic. No.: C69089 | 20722 SOUTH MAIN STREET CARSON, CA 90745 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 5/30/2024 | Conditional Approval | THOMAS FINNILA |
| Deputy Grading | 6/5/2024 | Partial Approval | THOMAS FINNILA |
| Deputy Other (see comments) | 6/13/2024 | Approved | THOMAS FINNILA |
| Deputy Other (see comments) | 6/14/2024 | Conditional Approval | THOMAS FINNILA |
| Piling/Pier/Caisson | 6/14/2024 | Partial Approval | THOMAS FINNILA |
| Deputy Other (see comments) | 6/17/2024 | Conditional Approval | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 6/17/2024 | Conditional Approval | THOMAS FINNILA |
| Deputy Other (see comments) | 6/21/2024 | Approved | THOMAS FINNILA |
| Piling/Pier/Caisson | 6/21/2024 | Partial Approval | THOMAS FINNILA |
| Deputy Grading | 6/24/2024 | Conditional Approval | THOMAS FINNILA |
| Deputy Other (see comments) | 6/26/2024 | Conditional Approval | THOMAS FINNILA |
| Deputy Shotcrete | 6/26/2024 | Conditional Approval | THOMAS FINNILA |
| Deputy Other (see comments) | 7/2/2024 | Conditional Approval | THOMAS FINNILA |
| Deputy Other (see comments) | 8/6/2024 | Conditional Approval | HENRY KIM |
| Deputy Other (see comments) | 8/13/2024 | Conditional Approval | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 8/23/2024 | Conditional Approval | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 10/15/2024 | Partial Approval | THOMAS FINNILA |
| Deputy Other (see comments) | 10/17/2024 | Conditional Approval | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 11/6/2024 | Partial Approval | SEAN WIRCH |
| Excavation/Setback/Form/Re-Bar | 4/4/2025 | Not Ready for Inspection | JOHN COLEMAN |
| Excavation/Setback/Form/Re-Bar | 4/10/2025 | Partial Approval | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 7/3/2025 | No Access for Inspection | JON MCHUGH |
| Gunite | 7/16/2025 | Corrections Issued | THOMAS FINNILA |
| Deputy Shotcrete | 7/21/2025 | Partial Approval | SEAN WIRCH |
| Excavation/Setback/Form/Re-Bar | 8/19/2025 | Approved | THOMAS FINNILA |
| Pool Piping | 8/21/2025 | Approved | JOHN KIDWELL |
| Deputy Shotcrete | 8/25/2025 | Conditional Approval | THOMAS FINNILA |
| Deputy Shotcrete | 12/12/2025 | Partial Approval | SEAN WIRCH |
| Grounding or Bonding | 2/24/2026 | Approved | THOMAS FINNILA |