310 N SKYEWIAY ROAD 90049
Certificate Information: 310 N SKYEWIAY ROAD 90049
- Application / Permit
- 21047-30000-01277
- Plan Check / Job No.
- B21WL02453
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New swimming pool and spa
- Permit Issued
- Issued on 7/7/2021
- Issuing Office
- Current Status
- CofO Issued on 9/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2021 | REZA HAGHIGHAT |
| Corrections Issued | 6/3/2021 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 7/6/2021 | JAHANSHAH POURHASSAN |
| Issued | 7/7/2021 | APPLICANT |
| CofO in Progress | 9/24/2022 | KEVIN SARGSYAN |
| Permit Finaled | 9/26/2022 | DANIEL ORRANTE |
| CofO Issued | 9/26/2022 | DANIEL ORRANTE |
| Permit Finaled | 9/26/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2021 | KATHLEEN LEE |
| Watercourse | Cleared | 6/14/2021 | KATHLEEN LEE |
| Grading Pre-Inspection | Cleared | 7/7/2021 | REZA HAGHIGHAT |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| FLOOD-Proofing Certificate | 4/21/2022 | Approved | JOHN KIDWELL |
| Pre-Gunite | 4/21/2022 | Approved | JOHN KIDWELL |
| Rough-Plumbing | 4/21/2022 | Approved | JOHN KIDWELL |
| Enclosure/Fence | 7/25/2022 | Approved | JUAN VALENZUELA |
| Grounding or Bonding | 7/25/2022 | Approved | JUAN VALENZUELA |
| Pool Equipment Noise Test | 9/19/2022 | Approved | JAMES VORHIS |
| Excavation/Setback/Form/Re-Bar | 9/21/2022 | Approved | KEVIN SARGSYAN |
| FLOOD-Elevation Certificate | 9/21/2022 | Approved | KEVIN SARGSYAN |
| Final | 9/21/2022 | Corrections Issued | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 9/21/2022 | SGSOV Approved | KEVIN SARGSYAN |
| Final | 9/23/2022 | OK to Issue CofO | KEVIN SARGSYAN |