130 N VISTA ST 90036
Certificate Information: 130 N VISTA ST 90036
- Application / Permit
- 21047-30000-01231
- Plan Check / Job No.
- B21WL02316
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New pool and spa per std. plan #268
- Permit Issued
- Issued on 10/18/2021
- Issuing Office
- Current Status
- CofO Issued on 7/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2021 | KHUONG TRUONG |
| Corrections Issued | 6/2/2021 | KHUONG TRUONG |
| Applicant returned to address corrections | 8/31/2021 | KHUONG TRUONG |
| Plan Check Approved | 9/10/2021 | ALFREDO JARA |
| Issued | 10/18/2021 | APPLICANT |
| CofO in Progress | 6/8/2022 | ALIZAH MAYAGOITIA |
| CofO in Progress | 6/8/2022 | ALIZAH MAYAGOITIA |
| Permit Finaled | 7/6/2022 | DEROLD HAUFF |
| CofO Issued | 7/6/2022 | DEROLD HAUFF |
| Permit Finaled | 7/6/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grounding or Bonding | 2/7/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Pre-Gunite | 2/7/2022 | Approved | CHRIS CHRISTENSEN |
| Gas Piping or Gas Test | 3/3/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| Gas Piping or Gas Test | 3/7/2022 | Approved | CHRIS CHRISTENSEN |
| Pre-Inspection | 3/25/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Grounding or Bonding | 3/30/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Grounding or Bonding | 3/31/2022 | Corrections Issued | ADAM ESCOTO |
| Grounding or Bonding | 4/5/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Enclosure/Fence | 4/11/2022 | Corrections Issued | STUART CHAPMAN |
| Grounding or Bonding | 4/11/2022 | Approved | STUART CHAPMAN |
| Enclosure/Fence | 4/27/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Enclosure/Fence | 5/4/2022 | Conditional Approval | JOSEPH MCGARRY |
| Final | 5/19/2022 | Not Ready for Inspection | ADAM ESCOTO |
| SGSOV-Seismic Gas S/O Valve | 5/19/2022 | SGSOV Not Ready | ADAM ESCOTO |
| Pool Equipment Noise Test | 6/3/2022 | Approved | JUSTIN CURTIS |
| Final | 6/7/2022 | Conditional Approval | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 6/7/2022 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Enclosure/Fence | 6/8/2022 | Approved | ALIZAH MAYAGOITIA |
| Final | 6/8/2022 | OK to Issue CofO | ALIZAH MAYAGOITIA |