444 N TUALLITAN ROAD 90049

Certificate Information: 444 N TUALLITAN ROAD 90049

Application / Permit
21047-30000-01217
Plan Check / Job No.
B21WL02273
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
new pool & spa 26' x 8' per eng. calc. & details
Permit Issued
Issued on 8/23/2021
Issuing Office
Current Status
CofO Issued on 7/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/26/2021 APPLICANT
Assigned to Plan Check Engineer 6/10/2021 KHUONG TRUONG
Corrections Issued 6/13/2021 KHUONG TRUONG
Quality Review Completed 6/21/2021 TARIK SAOUD
Plan Check Approved 8/3/2021 KHUONG TRUONG
Issued 8/23/2021 APPLICANT
CofO in Progress 7/19/2025 MICHAEL PELHAM
Permit Finaled 7/19/2025 RICHARD STEINBACH
CofO Issued 7/19/2025 RICHARD STEINBACH
Permit Finaled 7/19/2025 RICHARD STEINBACH

Permit Application Clearance Information

Sewer availability Cleared 6/23/2021 TRACY TATE
Grading Pre-Inspection Cleared 8/3/2021 KHUONG TRUONG
Eng Process Fee Ord 176,300 Cleared 8/12/2021 TRACY TATE

Contact Information

Contractor Farahi Construction Inc; Lic. No.: 584288-B 2933 BEVERLY GLEN CIRCLE      LOS ANGELES, CA 90077
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403
Engineer Salehipour,, Sassan Abolghasem; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 9/20/2021 Corrections Issued CHRISTOPHER WILSON
Pre-Gunite 9/21/2021 Approved JUAN VALENZUELA
Special/Order Compliance 9/21/2021 Partial Approval JESUS RODRIGUEZ
Special/Order Compliance 9/21/2021 Partial Inspection JAVIER RAMOS JR
Special/Order Compliance 9/21/2021 Partial Inspection MORRIS JACKSON
Deputy Shotcrete 9/24/2021 Conditional Approval JUAN VALENZUELA
Pre-Gunite 1/21/2022 Not Ready for Inspection JUAN VALENZUELA
Grounding or Bonding 4/6/2022 Approved JUAN VALENZUELA
Enclosure/Fence 7/14/2022 Corrections Issued JUAN VALENZUELA
Enclosure/Fence 7/26/2022 Approved JUAN VALENZUELA
Final 8/31/2022 Corrections Issued JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 8/31/2022 SGSOV Not Ready JUAN VALENZUELA
Pool Equipment Noise Test 9/2/2022 Approved JAMES VORHIS
Final 9/19/2022 Not Ready for Inspection JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 9/19/2022 SGSOV Approved JUAN VALENZUELA
Final 7/19/2025 OK to Issue CofO MICHAEL PELHAM