991 S WELLESLEY AVE 90049

Certificate Information: 991 S WELLESLEY AVE 90049

Application / Permit
21047-30000-01018
Plan Check / Job No.
B21WL01926
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
New swimming pool and spa per standard plan #268
Permit Issued
Issued on 10/18/2021
Issuing Office
Current Status
CofO Issued on 7/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/10/2021 APPLICANT
Assigned to Plan Check Engineer 5/26/2021 HOOMAN HAJIZADEH
Corrections Issued 6/11/2021 HOOMAN HAJIZADEH
Quality Review Completed 6/21/2021 TARIK SAOUD
Applicant returned to address corrections 10/7/2021 HOOMAN HAJIZADEH
Plan Check Approved 10/8/2021 HOOMAN HAJIZADEH
Issued 10/18/2021 APPLICANT
CofO in Progress 7/14/2022 OGANES TARAKHCHYAN
Permit Finaled 7/23/2022 DANIEL ORRANTE
CofO Issued 7/23/2022 DANIEL ORRANTE
Permit Finaled 7/23/2022 DANIEL ORRANTE

Permit Application Clearance Information

Watercourse Cleared 8/13/2021 MAHELET GEBEYHU
Eng Process Fee Ord 176,300 Cleared 8/18/2021 MAHELET GEBEYHU
Hold Cleared 1/3/2022 JASON SHEETS

Contact Information

Contractor Decardo'S Pools And Landscape Inc; Lic. No.: 532429-C27 23705 VANOWEN ST #114      WEST HILLS, CA 91307
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807
Engineer Markov,, George P; Lic. No.: C55855 1623 THOMPSON AVE      GLENDALE, CA 91201

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/24/2022 Approved OGANES TARAKHCHYAN
FLOOD-Elevation Certificate 1/24/2022 Approved OGANES TARAKHCHYAN
FLOOD-Proofing Certificate 1/24/2022 Approved OGANES TARAKHCHYAN
Pool Piping 1/24/2022 Approved OGANES TARAKHCHYAN
Pre-Gunite 1/24/2022 Approved OGANES TARAKHCHYAN
Rough-Plumbing 1/24/2022 Approved OGANES TARAKHCHYAN
Deputy Shotcrete 1/31/2022 Partial Approval OGANES TARAKHCHYAN
Deck 2/16/2022 Approved OGANES TARAKHCHYAN
Enclosure/Fence 5/24/2022 Approved OGANES TARAKHCHYAN
Equipment Noise Level 6/8/2022 Approved AGUSTIN ALVAREZMORALES
Final 6/9/2022 Corrections Issued JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 6/9/2022 SGSOV Not Ready JOHN KIDWELL
Final 6/28/2022 Corrections Issued OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 6/28/2022 SGSOV Approved OGANES TARAKHCHYAN
Final 7/11/2022 Not Ready for Inspection STEPHANIE SWANSON
Final 7/13/2022 OK to Issue CofO OGANES TARAKHCHYAN