4607 E ALUMNI AVE 90041
Certificate Information: 4607 E ALUMNI AVE 90041
- Application / Permit
- 21047-30000-00749
- Plan Check / Job No.
- B21WL01469
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New pool ( 18'X10') and spa (6'X6') per standard plan # 268
- Permit Issued
- Issued on 4/19/2021
- Issuing Office
- Current Status
- CofO Issued on 9/3/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/7/2021 | ALFREDO JARA |
| Plan Check Approved | 4/7/2021 | ALFREDO JARA |
| Issued | 4/19/2021 | APPLICANT |
| CofO in Progress | 8/19/2021 | CRAIG VAUGHAN |
| Permit Finaled | 9/3/2021 | DEROLD HAUFF |
| Permit Finaled | 9/3/2021 | DEROLD HAUFF |
| CofO Issued | 9/3/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/7/2021 | ALFREDO JARA |
Contact Information
| Contractor | Sunset Built Inc; Lic. No.: 1005054-B | 5455 WILSHIRE BLVD #1811 LOS ANGELES, CA 90036 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grounding or Bonding | 5/4/2021 | Partial Approval | CRAIG VAUGHAN |
| Pre-Gunite | 5/4/2021 | Approved | CRAIG VAUGHAN |
| Rough-Electrical | 5/4/2021 | Partial Approval | CRAIG VAUGHAN |
| Rough-Plumbing | 5/4/2021 | Approved | CRAIG VAUGHAN |
| Deputy Shotcrete | 5/13/2021 | No Access for Inspection | CRAIG VAUGHAN |
| Enclosure/Fence | 7/19/2021 | Corrections Issued | BRIAN SULLIVAN |
| Grounding or Bonding | 7/19/2021 | Approved | BRIAN SULLIVAN |
| Enclosure/Fence | 7/26/2021 | Approved | BRIAN SULLIVAN |
| Equipment Noise Level | 8/2/2021 | Not Ready for Inspection | RYAN TAGUINES |
| SGSOV-Seismic Gas S/O Valve | 8/4/2021 | SGSOV Not Ready | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 8/17/2021 | Approved | CRAIG VAUGHAN |
| Final | 8/17/2021 | Conditional Approval | CRAIG VAUGHAN |
| Pool Equipment Noise Test | 8/17/2021 | Approved | RYAN TAGUINES |
| SGSOV-Seismic Gas S/O Valve | 8/17/2021 | SGSOV Approved | CRAIG VAUGHAN |