17371 W CHASE ST 91325

Certificate Information: 17371 W CHASE ST 91325

Application / Permit
21047-30000-00708
Plan Check / Job No.
B21WL01361
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(N) SWIMMING POOL & SPA, PER STANDARD PLAN #268
Permit Issued
Issued on 8/14/2021
Issuing Office
Current Status
CofO Issued on 9/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/31/2021 APPLICANT
Assigned to Plan Check Engineer 4/5/2021 KHUONG TRUONG
Corrections Issued 4/5/2021 KHUONG TRUONG
Applicant returned to address corrections 4/21/2021 JASON JANGADA
Applicant returned to address corrections 4/28/2021 JASON JANGADA
Applicant returned to address corrections 5/9/2021 DAVID CASTILLO
Plan Check Approved 6/4/2021 DAVID CASTILLO
Issued 8/14/2021 APPLICANT
CofO in Progress 9/1/2022 JAVIER RAMOS JR
CofO in Progress 9/6/2022 ROBERT GOLD
CofO Issued 9/6/2022 MICHAEL SMITH
Permit Finaled 9/6/2022 MICHAEL SMITH

Permit Application Clearance Information

Metro Rail approval Cleared 4/15/2021 KHUONG TRUONG

Contact Information

Contractor J H J Construction; Lic. No.: 589967-B 671 ARMSTEAD STREET      GLENDORA, CA 91740

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 9/21/2021 Approved MARK JOHNSON
Deputy Shotcrete 9/23/2021 Conditional Approval MARK JOHNSON
Rough-Electrical 10/20/2021 Approved MARK JOHNSON
Deck 12/1/2021 Approved CHRISTOPHER DELLEFIELD
Grounding or Bonding 12/1/2021 Approved CHRISTOPHER DELLEFIELD
Enclosure/Fence 2/14/2022 Corrections Issued JESUS RODRIGUEZ
Enclosure/Fence 3/1/2022 Approved MICHAEL TEMPLE
Excavation/Setback/Form/Re-Bar 5/3/2022 Not Ready for Inspection JAVIER RAMOS JR
Final 5/3/2022 Corrections Issued JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 5/3/2022 SGSOV Not Ready JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 5/10/2022 Approved RAUL OLAGI
Final 5/10/2022 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 5/10/2022 SGSOV Approved RAUL OLAGI
Pool Equipment Noise Test 6/23/2022 Approved ALFREDO FLORES
Final 6/29/2022 OK to Issue CofO JAVIER RAMOS JR