331 S ANITA AVE 90049
Certificate Information: 331 S ANITA AVE 90049
- Application / Permit
- 21047-30000-00498
- Plan Check / Job No.
- B21WL00989
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- New swimming pool at rear of the lot
- Permit Issued
- Issued on 7/12/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2021 | REZA HAGHIGHAT |
| Corrections Issued | 5/10/2021 | REZA HAGHIGHAT |
| Quality Review Completed | 5/26/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 10/21/2021 | REZA HAGHIGHAT |
| Building Plans Picked Up | 12/27/2021 | APPLICANT |
| Plan Check Approved | 4/6/2022 | REZA HAGHIGHAT |
| Issued | 7/12/2023 | APPLICANT |
| CofO in Progress | 7/18/2025 | HERBERT GIRON |
| Permit Finaled | 7/29/2025 | RICHARD STEINBACH |
| CofO Issued | 7/29/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/29/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| ZA Case | Cleared | 8/10/2021 | LOUIS ORTEGA |
| Grading Pre-Inspection | Cleared | 4/6/2022 | REZA HAGHIGHAT |
Contact Information
| Contractor | Mlr Development Corporation; Lic. No.: 1027283-B | 15720 VENTURA BLVD SUITE 405 ENCINO, CA 91436 |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
| Engineer | Dermendjian,, Raffi Hrag; Lic. No.: C88261 | 9325 SHOSHONE AVENUE NORTHRIDGE, CA 91325 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/23/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Pool Piping | 8/23/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 9/6/2024 | Approved | JESUS RODRIGUEZ |
| Pool Piping | 9/6/2024 | Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 9/6/2024 | Partial Inspection | MICHAEL ALLEN |
| Gas Piping or Gas Test | 10/11/2024 | Approved | JESUS RODRIGUEZ |
| Grounding or Bonding | 10/17/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Enclosure/Fence | 2/3/2025 | Approved | JESUS RODRIGUEZ |
| Final | 5/29/2025 | Corrections Issued | HERBERT GIRON |
| Pre-Gunite | 5/29/2025 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 5/29/2025 | SGSOV Not Ready | HERBERT GIRON |
| Equipment Noise Level | 6/2/2025 | Not Ready for Inspection | JAMES VORHIS |
| Pool Equipment Noise Test | 6/4/2025 | Approved | EUSEBIO GUZMAN |
| Final | 6/6/2025 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 6/6/2025 | SGSOV Approved | HERBERT GIRON |
| Final | 7/17/2025 | OK to Issue CofO | HERBERT GIRON |