7901 W ZEUS DR 90046
Certificate Information: 7901 W ZEUS DR 90046
- Application / Permit
- 21047-30000-00331
- Plan Check / Job No.
- B21WL00664
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- 1 of 2 (n) swimming pool & spa per engr. plans.
- Permit Issued
- Issued on 11/14/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/21/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/18/2021 | ALFREDO JARA |
| Corrections Issued | 2/23/2021 | ALFREDO JARA |
| Building Plans Picked Up | 3/4/2021 | APPLICANT |
| Plan Check Approved | 10/21/2022 | KHUONG TRUONG |
| Issued | 11/14/2022 | APPLICANT |
| CofO in Progress | 1/11/2024 | RAUL BARAJAS |
| CofO Issued | 1/21/2024 | DEROLD HAUFF |
| Permit Finaled | 1/21/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/21/2022 | ALFREDO JARA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Azizisefat,, Solayman; Lic. No.: C57840 | 19510 VENTURA BLVD STE 110 TARZANA, CA 91356 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 5/16/2023 | Approved | STUART CHAPMAN |
| Gas Piping or Gas Test | 6/21/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Rough-Electrical | 6/21/2023 | Approved | STUART CHAPMAN |
| Deck | 8/8/2023 | Approved | RAUL BARAJAS |
| Enclosure/Fence | 9/11/2023 | Corrections Issued | BRIAN SULLIVAN |
| Enclosure/Fence | 9/12/2023 | Partial Approval | RAUL BARAJAS |
| Gas Piping or Gas Test | 10/19/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Gas Piping or Gas Test | 11/17/2023 | Approved | STUART CHAPMAN |
| Equipment Noise Level | 11/21/2023 | Approved | DA LIU |
| SGSOV-Seismic Gas S/O Valve | 11/22/2023 | SGSOV Not Ready | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 11/29/2023 | Approved | RAUL BARAJAS |
| Final | 11/29/2023 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 11/29/2023 | SGSOV Approved | RAUL BARAJAS |
| Final | 1/11/2024 | OK to Issue CofO | RAUL BARAJAS |