1507 N BUNDY DR 90049

Certificate Information: 1507 N BUNDY DR 90049

Application / Permit
21047-30000-00325
Plan Check / Job No.
B21WL00652
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(N) Pool (28.5' x 14') and Spa ( 7'x6')Per standard plans#268
Permit Issued
Issued on 7/13/2021
Issuing Office
Current Status
CofO Issued on 2/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/16/2021 APPLICANT
Assigned to Plan Check Engineer 2/24/2021 ALFREDO JARA
Corrections Issued 2/24/2021 ALFREDO JARA
Building Plans Picked Up 2/25/2021 APPLICANT
Plan Check Approved 4/9/2021 ALFREDO JARA
Issued 7/13/2021 APPLICANT
CofO in Progress 12/18/2022 JUAN VALENZUELA
Permit Finaled 2/8/2023 DANIEL ORRANTE
CofO Issued 2/8/2023 DANIEL ORRANTE
Permit Finaled 2/8/2023 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/9/2021 ALFREDO JARA

Contact Information

Contractor Shirley David M Construction Corporation; Lic. No.: 602138-B 11693 SAN VICENTE BLVE #905      LOS ANGELES, CA 90049
Engineer Nadasdi,, Kristof; Lic. No.: C64525 5952 SW RIVERIDGE LN      PORTLAND, OR 97239
Engineer Shirley,, Peter Franklin; Lic. No.: C75050 4429 DAWES AVE      CULVER CITY, CA 90230

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/2/2021 Approved JUAN VALENZUELA
FLOOD-Elevation Certificate 9/2/2021 Approved JUAN VALENZUELA
FLOOD-Proofing Certificate 9/2/2021 Approved JUAN VALENZUELA
Pre-Gunite 9/2/2021 Approved JUAN VALENZUELA
Rough-Electrical 9/2/2021 Partial Approval JUAN VALENZUELA
Rough-Plumbing 9/2/2021 Partial Approval JUAN VALENZUELA
Deputy Shotcrete 9/14/2021 Conditional Approval JESUS RODRIGUEZ
Gas Piping or Gas Test 12/9/2021 Approved ANDREW NAVE
Deck 12/23/2021 Approved JUAN VALENZUELA
Enclosure/Fence 5/23/2022 Approved JUAN VALENZUELA
Pool Equipment Noise Test 6/1/2022 Approved JAMES VORHIS
Final 9/9/2022 Conditional Approval JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 9/9/2022 SGSOV Approved JUAN VALENZUELA
Final 12/16/2022 OK to Issue CofO JUAN VALENZUELA