618 N CRESCENT HEIGHTS BLVD 90048

Certificate Information: 618 N CRESCENT HEIGHTS BLVD 90048

Application / Permit
21047-20000-02850
Plan Check / Job No.
B21VN18104
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 17' X 23' SWIMMING POOL AND 4' X 7' SPA WITHIN PER STANDARD PLAN #268 AND ENGINEER DETAIL
Permit Issued
Issued on 3/31/2022
Issuing Office
Current Status
CofO Issued on 10/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2021 APPLICANT
Assigned to Plan Check Engineer 12/30/2021 JEROME MAGAT PALMA
Corrections Issued 12/31/2021 JEROME MAGAT PALMA
Plan Check Approved 3/31/2022 JEROME MAGAT PALMA
Issued 3/31/2022 APPLICANT
Building Plans Picked Up 3/31/2022 APPLICANT
CofO in Progress 9/30/2022 MICHAEL LEWIS
Permit Finaled 10/15/2022 DEROLD HAUFF
CofO Issued 10/15/2022 DEROLD HAUFF
Permit Finaled 10/15/2022 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 3/24/2022 RIDWAN HARDY
Construction within easement Cleared 3/24/2022 RIDWAN HARDY

Contact Information

Contractor Avanti Pools Inc; Lic. No.: 772516-C53 8138 ORION AVE      VAN NUYS, CA 91406
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 5/5/2022 Corrections Issued ADAM ESCOTO
Excavation/Setback/Form/Re-Bar 5/23/2022 Approved JOSEPH MCGARRY
Grounding or Bonding 5/23/2022 Partial Approval JOSEPH MCGARRY
Pre-Gunite 5/23/2022 Approved JOSEPH MCGARRY
Rough-Plumbing 5/23/2022 Partial Approval JOSEPH MCGARRY
Deputy Shotcrete 6/2/2022 Conditional Approval ADAM ESCOTO
Deck 7/18/2022 Approved ALIZAH MAYAGOITIA
Grounding or Bonding 7/18/2022 Approved ALIZAH MAYAGOITIA
Enclosure/Fence 8/9/2022 Corrections Issued JOSEPH MCGARRY
Enclosure/Fence 8/12/2022 Corrections Issued MICHAEL LEWIS
Enclosure/Fence 8/17/2022 Approved MICHAEL LEWIS
Equipment Noise Level 9/13/2022 Approved ZEYDI STEWART
Final 9/16/2022 Corrections Issued MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 9/16/2022 SGSOV Approved MICHAEL LEWIS
Final 9/26/2022 OK to Issue CofO MICHAEL LEWIS