1309 E PALMS BLVD 90291
Certificate Information: 1309 E PALMS BLVD 90291
- Application / Permit
- 21047-20000-02849
- Plan Check / Job No.
- B21VN18103
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- 16'X33.5' POOL, 6' DEEP W/ 7'X7' SPA, 3.5' DEEP PER LA STD PLAN 268
- Permit Issued
- Issued on 2/11/2022
- Issuing Office
- Current Status
- CofO Issued on 12/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2021 | COLIN LOREDO |
| Corrections Issued | 12/31/2021 | COLIN LOREDO |
| Plan Check Approved | 2/10/2022 | COLIN LOREDO |
| Issued | 2/11/2022 | APPLICANT |
| CofO in Progress | 12/8/2023 | HERBERT GIRON |
| Permit Finaled | 12/18/2023 | DANIEL ORRANTE |
| CofO Issued | 12/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 12/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZA Case | Cleared | 1/31/2022 | MIGUEL GAMBOA |
| Grading Pre-Inspection | Cleared | 2/10/2022 | COLIN LOREDO |
Contact Information
| Contractor | Avanti Pools Inc; Lic. No.: 772516-C53 | 8138 ORION AVE VAN NUYS, CA 91406 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 3/15/2022 | Approved | DAVID FEILER |
| Deck | 7/29/2022 | Not Ready for Inspection | DAVID FEILER |
| Enclosure/Fence | 7/29/2022 | Corrections Issued | DAVID FEILER |
| Grounding or Bonding | 7/29/2022 | Corrections Issued | DAVID FEILER |
| Deck | 9/15/2022 | Approved | STEPHANIE SWANSON |
| Enclosure/Fence | 9/15/2022 | Corrections Issued | STEPHANIE SWANSON |
| Grounding or Bonding | 9/15/2022 | Approved | STEPHANIE SWANSON |
| Equipment Noise Level | 12/22/2022 | Approved | AGUSTIN ALVAREZMORALES |
| Excavation/Setback/Form/Re-Bar | 12/27/2022 | Approved | EVAN COOPER |
| Final | 12/27/2022 | Corrections Issued | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 12/27/2022 | SGSOV Approved | EVAN COOPER |
| Pre-Inspection | 7/19/2023 | Approved | EVAN COOPER |
| Final | 11/30/2023 | Corrections Issued | HERBERT GIRON |
| Final | 12/7/2023 | OK to Issue CofO | HERBERT GIRON |