10119 W PETALUMA PL 91352

Certificate Information: 10119 W PETALUMA PL 91352

Application / Permit
21047-20000-02780
Plan Check / Job No.
B21VN17679
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 14'X28' POOL WITH A RAISED 8'X5' SPA PER LA STANDARD PLAN 268
Permit Issued
Issued on 12/28/2021
Issuing Office
Current Status
CofO Issued on 1/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2021 APPLICANT
Assigned to Plan Check Engineer 12/21/2021 COLIN LOREDO
Plan Check Approved 12/22/2021 COLIN LOREDO
Corrections Issued 12/25/2021 COLIN LOREDO
Issued 12/28/2021 APPLICANT
CofO in Progress 11/28/2022 DAVID ANDERSON
CofO Issued 1/18/2023 MICHAEL SMITH
Permit Finaled 1/18/2023 MICHAEL SMITH

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Titan Builders & Remodeling Inc; Lic. No.: 1002561-B 4872 TOPANGA CANYON BLVD #4      WOODLAND HILLS, CA 91364

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/28/2022 Not Ready for Inspection JOHN HAYES
Rough-Electrical 1/28/2022 Not Ready for Inspection JOHN HAYES
Rough-Plumbing 1/28/2022 Not Ready for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 2/4/2022 Approved GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 2/4/2022 Off-Hour Fees Due
Gas Piping or Gas Test 2/4/2022 Approved GREGG CUMMINGS
Grounding or Bonding 2/4/2022 Approved GREGG CUMMINGS
Pool Piping 2/4/2022 Approved GREGG CUMMINGS
Rough-Electrical 2/4/2022 Off-Hour Fees Due
Rough-Electrical 2/4/2022 Partial Approval GREGG CUMMINGS
Rough-Plumbing 2/4/2022 Approved GREGG CUMMINGS
Rough-Plumbing 2/4/2022 Off-Hour Fees Due
Grounding or Bonding 3/4/2022 Corrections Issued MATTHEW NELSON
Grounding or Bonding 3/9/2022 Not Ready for Inspection GREGG CUMMINGS
Grounding or Bonding 3/14/2022 Approved JAVIER RAMOS JR
Enclosure/Fence 6/14/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Enclosure/Fence 7/6/2022 Approved DAVID ANDERSON
Final 7/22/2022 Not Ready for Inspection DAVID ANDERSON
Pre-Gunite 7/22/2022 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 7/22/2022 SGSOV Approved DAVID ANDERSON
Final 9/28/2022 Conditional Approval DAVID ANDERSON
Equipment Noise Level 10/6/2022 Corrections Issued DAVID ANDERSON
Pool Equipment Noise Test 10/14/2022 Approved FELIPE PENICHE
Final 11/23/2022 OK to Issue CofO DAVID ANDERSON