8929 W HARGIS ST 90034
Certificate Information: 8929 W HARGIS ST 90034
- Application / Permit
- 21047-20000-02728
- Plan Check / Job No.
- B21VN17371
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 30'X16' POOL AND 9'X7' SPA PER LA STANDARD PLAN 268
- Permit Issued
- Issued on 1/19/2022
- Issuing Office
- Current Status
- CofO Issued on 5/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2021 | COLIN LOREDO |
| Plan Check Approved | 12/23/2021 | COLIN LOREDO |
| Building Plans Picked Up | 12/29/2021 | APPLICANT |
| Issued | 1/19/2022 | APPLICANT |
| CofO in Progress | 5/3/2022 | KENNETH NAGLE |
| Permit Finaled | 5/4/2022 | DANIEL ORRANTE |
| CofO Issued | 5/4/2022 | DANIEL ORRANTE |
| Permit Finaled | 5/4/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Custom Derian Pools & Construction; Lic. No.: 977981-C53 | PO BOX 1352 MOORPARK, CA 93020 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/21/2022 | Corrections Issued | EVAN COOPER |
| Gas Piping or Gas Test | 1/25/2022 | Not Ready for Inspection | EVAN COOPER |
| Pre-Gunite | 1/25/2022 | Approved | EVAN COOPER |
| Rough-Electrical | 1/25/2022 | Not Ready for Inspection | EVAN COOPER |
| Gas Piping or Gas Test | 2/8/2022 | Approved | EVAN COOPER |
| Rough-Electrical | 2/8/2022 | Approved | EVAN COOPER |
| Solar System | 2/8/2022 | Not Ready for Inspection | EVAN COOPER |
| Deck | 3/1/2022 | Approved | EVAN COOPER |
| Enclosure/Fence | 3/29/2022 | Corrections Issued | EVAN COOPER |
| Enclosure/Fence | 4/6/2022 | Corrections Issued | EVAN COOPER |
| Enclosure/Fence | 4/8/2022 | Approved | EVAN COOPER |
| Pool Equipment Noise Test | 4/19/2022 | Approved | AGUSTIN ALVAREZMORALES |
| SGSOV-Seismic Gas S/O Valve | 4/19/2022 | SGSOV Not Ready | EVAN COOPER |
| ELECTRICAL-Final | 4/22/2022 | Approved | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 4/22/2022 | Approved | EVAN COOPER |
| Final | 4/22/2022 | Corrections Issued | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 4/22/2022 | SGSOV Approved | EVAN COOPER |
| Final | 5/3/2022 | OK to Issue CofO | KENNETH NAGLE |