13550 W HARTLAND ST 91405
Certificate Information: 13550 W HARTLAND ST 91405
- Application / Permit
- 21047-20000-02720
- Plan Check / Job No.
- B21VN17282
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 30'-0" x 18'-0" POOL WITH A 9'-0" X 9'-0" SPA PER CITY STD. PLAN # 268 AND ENGINEERING DETAILS
- Permit Issued
- Issued on 2/10/2022
- Issuing Office
- Current Status
- CofO Issued on 8/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/15/2021 | ALFRED RAMIREZ |
| Corrections Issued | 12/15/2021 | ALFRED RAMIREZ |
| Issued | 2/10/2022 | APPLICANT |
| Building Plans Picked Up | 2/14/2022 | APPLICANT |
| CofO in Progress | 6/10/2022 | CHRISTOPHE COCHRAN |
| CofO in Progress | 6/10/2022 | CHRISTOPHE COCHRAN |
| Permit Finaled | 8/4/2022 | DANIEL ORRANTE |
| CofO Issued | 8/4/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/4/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 3/2/2022 | Approved | CHRISTOPHE COCHRAN |
| Rough-Plumbing | 3/2/2022 | Approved | CHRISTOPHE COCHRAN |
| Deputy Shotcrete | 3/8/2022 | Conditional Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 4/18/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Enclosure/Fence | 4/18/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Gas Piping or Gas Test | 4/18/2022 | Approved | CHRISTOPHE COCHRAN |
| Enclosure/Fence | 4/22/2022 | Approved | CHRISTOPHE COCHRAN |
| Equipment Noise Level | 5/25/2022 | Approved | FELIPE PENICHE |
| Excavation/Setback/Form/Re-Bar | 5/27/2022 | Approved | ARAM AVEDISIAN |
| Final | 5/27/2022 | Corrections Issued | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 5/27/2022 | SGSOV Not Ready | ARAM AVEDISIAN |
| Final | 6/9/2022 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 6/9/2022 | SGSOV Approved | CHRISTOPHE COCHRAN |