14633 W ROUND VALLEY DR 91403

Certificate Information: 14633 W ROUND VALLEY DR 91403

Application / Permit
21047-20000-02701
Plan Check / Job No.
B21VN17157
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 15'x32' POOL AND SPA ON PILES PER ENGINEERING DESIGN
Permit Issued
Issued on 6/30/2022
Issuing Office
Current Status
CofO Issued on 1/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/9/2021 APPLICANT
Assigned to Plan Check Engineer 1/21/2022 SEAN SHAHMIRI
Corrections Issued 1/24/2022 SEAN SHAHMIRI
Quality Review Completed 1/24/2022 OMID HEDAYAT
Building Plans Picked Up 1/24/2022 APPLICANT
Applicant returned to address corrections 4/28/2022 SEAN SHAHMIRI
Plan Check Approved 4/28/2022 SEAN SHAHMIRI
Issued 6/30/2022 APPLICANT
CofO in Progress 12/4/2024 JACK KARGODORIAN
Permit Finaled 1/9/2025 RUBEN SALAS
CofO Issued 1/9/2025 RUBEN SALAS
Permit Finaled 1/9/2025 RUBEN SALAS

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Azadi,, Bijan; Lic. No.: C18972 2825 PLAZA DEL AMO # 179      TORRANCE, CA 90503
Contractor Royal Moon Pools Inc; Lic. No.: 1041907-C53 2518 SAN MACHID WAY      ROSAMOND, CA 93560
Engineer Cristescu,, Barbu D; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401
Engineer Lin,, Chi Hsin; Lic. No.: GE2921 1722 CEDAR STREET APT G      ALHAMBRA, CA 91801

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 9/7/2022 Approved JACK KARGODORIAN
Deputy Other (see comments) 10/13/2022 Conditional Approval THOMAS FINNILA
Piling/Pier/Caisson 10/18/2022 Partial Approval THOMAS FINNILA
Pool Piping 12/7/2022 Conditional Approval THOMAS FINNILA
Deputy Shotcrete 12/9/2022 Conditional Approval MICHAEL SMITH
Deputy Other (see comments) 2/23/2023 Conditional Approval DAVID MATSON
Rough-Plumbing 6/27/2024 Approved VINCENT HANLEY
Gas Piping or Gas Test 8/8/2024 Partial Approval JACK KARGODORIAN
Enclosure/Fence 9/9/2024 Approved CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 10/1/2024 Approved JACK KARGODORIAN
Final 10/1/2024 Partial Approval JACK KARGODORIAN
Pre-Gunite 10/1/2024 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 10/1/2024 SGSOV Approved JACK KARGODORIAN
Final 11/21/2024 OK to Issue CofO JACK KARGODORIAN