3676 N CROWNRIDGE DR 91403
Certificate Information: 3676 N CROWNRIDGE DR 91403
- Application / Permit
- 21047-20000-02689
- Plan Check / Job No.
- B21VN17094
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 32'-2" X 18'-6" POOL WITH 5' X 18'-6" SPA ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 4/12/2022
- Issuing Office
- Current Status
- CofO Issued on 5/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2022 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 2/23/2022 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 2/25/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 2/28/2022 | APPLICANT |
| Plan Check Approved | 4/12/2022 | SEWADA ZADOORAN MILAGARDI |
| Issued | 4/12/2022 | APPLICANT |
| CofO in Progress | 5/16/2023 | VINCENT HANLEY |
| Permit Finaled | 5/17/2023 | JOHN JANSON |
| CofO Issued | 5/17/2023 | JOHN JANSON |
| Permit Finaled | 5/17/2023 | JOHN JANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/21/2022 | SEWADA ZADOORAN MILAGARDI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/10/2022 | Approved | DAVID SANDOVAL |
| Pool Piping | 5/10/2022 | Approved | DAVID SANDOVAL |
| Pre-Gunite | 5/10/2022 | Approved | DAVID SANDOVAL |
| Rough-Plumbing | 5/10/2022 | Approved | DAVID SANDOVAL |
| Deputy Shotcrete | 5/17/2022 | Conditional Approval | DAVID SANDOVAL |
| Grounding or Bonding | 9/23/2022 | Approved | JESUS PINEDA |
| Enclosure/Fence | 1/18/2023 | Corrections Issued | VINCENT HANLEY |
| Enclosure/Fence | 2/27/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 4/7/2023 | Approved | VINCENT HANLEY |
| Final | 4/7/2023 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 4/7/2023 | SGSOV Approved | VINCENT HANLEY |
| Equipment Noise Level | 4/13/2023 | Approved | ALFREDO FLORES |
| Final | 5/16/2023 | OK to Issue CofO | VINCENT HANLEY |