10514 N KEWEN AVE 91331
Certificate Information: 10514 N KEWEN AVE 91331
- Application / Permit
- 21047-20000-02671
- Plan Check / Job No.
- B21VN17008
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 16' X 26' IRREGULAR SHAPED POOL AND SPA PER LA CITY STD PLAN No. 265
- Permit Issued
- Issued on 6/17/2022
- Issuing Office
- Current Status
- CofO Issued on 7/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2021 | LUISANGEL VALENZUELA |
| Corrections Issued | 12/9/2021 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 12/27/2021 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 1/13/2022 | PINANK PATEL |
| Applicant returned to address corrections | 1/24/2022 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 3/25/2022 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 4/12/2022 | LUISANGEL VALENZUELA |
| Plan Check Approved | 5/23/2022 | LUISANGEL VALENZUELA |
| Building Plans Picked Up | 6/8/2022 | APPLICANT |
| Issued | 6/17/2022 | APPLICANT |
| CofO in Progress | 7/28/2022 | MICHEL ABAJAN |
| Permit Finaled | 7/29/2022 | DANIEL ORRANTE |
| CofO Issued | 7/29/2022 | DANIEL ORRANTE |
| Permit Finaled | 7/29/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/15/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Deed'S Pools; Lic. No.: 1036304-C53 | 7456 RADFORD AVE NORTH HOLLYWOOD, CA 91605 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 6/22/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| Grounding or Bonding | 6/22/2022 | Approved | MICHEL ABAJAN |
| Pool Piping | 6/22/2022 | Approved | MICHEL ABAJAN |
| Pool Piping | 6/22/2022 | Partial Inspection | MICHEL ABAJAN |
| Pre-Gunite | 6/22/2022 | Approved | MICHEL ABAJAN |
| Rough-Plumbing | 6/22/2022 | Corrections Issued | MICHEL ABAJAN |
| Deck | 7/8/2022 | Approved | MICHEL ABAJAN |
| Gas Piping or Gas Test | 7/8/2022 | Approved | MICHEL ABAJAN |
| Pool Piping | 7/8/2022 | Approved | MICHEL ABAJAN |
| Rough-Electrical | 7/8/2022 | Partial Approval | MICHEL ABAJAN |
| Rough-Plumbing | 7/8/2022 | Partial Approval | MICHEL ABAJAN |
| Enclosure/Fence | 7/19/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 7/25/2022 | Approved | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 7/25/2022 | Approved | MICHEL ABAJAN |
| Final | 7/25/2022 | OK to Issue CofO | MICHEL ABAJAN |
| Pool Equipment Noise Test | 7/25/2022 | Approved | FELIPE PENICHE |
| SGSOV-Seismic Gas S/O Valve | 7/25/2022 | SGSOV Approved | MICHEL ABAJAN |