18038 W BLUE SAIL DR 90272

Certificate Information: 18038 W BLUE SAIL DR 90272

Application / Permit
21047-20000-02669
Plan Check / Job No.
B21VN16974
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(N) POOL W/ TANNING SHELF (IRR 41' X 18'-5") & SPA (10' X 13'- 3/4") ON PILES PER ENG'R DESIGN
Permit Issued
Issued on 8/11/2022
Issuing Office
Valley
Current Status
CofO Issued on 1/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/7/2021 APPLICANT
Assigned to Plan Check Engineer 1/13/2022 NILOOFAR MEHRAIN
Corrections Issued 1/18/2022 NILOOFAR MEHRAIN
Quality Review Completed 1/21/2022 STEVEN KIM
Building Plans Picked Up 1/25/2022 APPLICANT
Applicant returned to address corrections 6/21/2022 NILOOFAR MEHRAIN
Plan Check Approved 7/13/2022 NILOOFAR MEHRAIN
Issued 8/11/2022 APPLICANT
CofO in Progress 12/22/2023 EVAN COOPER
Permit Finaled 1/2/2024 DANIEL ORRANTE
CofO Issued 1/2/2024 DANIEL ORRANTE
Permit Finaled 1/2/2024 DANIEL ORRANTE

Permit Application Clearance Information

Coastal Zone Cleared 5/31/2022 MIGUEL GAMBOA
Miscellaneous Cleared 5/31/2022 MIGUEL GAMBOA
Miscellaneous Cleared 5/31/2022 MIGUEL GAMBOA
ZI Cleared 5/31/2022 MIGUEL GAMBOA
Grading Pre-Inspection Cleared 6/21/2022 NILOOFAR MEHRAIN

Contact Information

Contractor Resto Group The; Lic. No.: 898290-B 311 N ROBERTSON SUITE 732      BEVERLY HILLS, CA 90211
Engineer Kessler,, Dale Edward; Lic. No.: C58524 16043 HART ST      VAN NUYS, CA 91406

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/15/2022 Approved BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 9/27/2022 Partial Approval BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 11/4/2022 Partial Approval BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 12/13/2022 Corrections Issued BRENDAN LOONEY
Pre-Gunite 12/13/2022 Not Ready for Inspection BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 12/19/2022 Approved MICHAEL PELHAM
Grounding or Bonding 12/19/2022 Partial Approval MICHAEL PELHAM
Pool Piping 12/19/2022 Partial Approval MICHAEL PELHAM
Pre-Gunite 12/19/2022 Approved MICHAEL PELHAM
Gas Piping or Gas Test 1/24/2023 Approved MICHAEL PELHAM
Rough-Electrical 1/24/2023 Approved MICHAEL PELHAM
Rough-Plumbing 1/24/2023 Approved MICHAEL PELHAM
Deputy Shotcrete 5/17/2023 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Gas Piping or Gas Test 5/31/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Rough-Electrical 5/31/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Rough-Plumbing 5/31/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Pool Equipment Noise Test 6/7/2023 Not Ready for Inspection JAMES VORHIS
Pool Piping 6/8/2023 Approved KENNETH NAGLE
Enclosure/Fence 9/15/2023 Corrections Issued KENNETH NAGLE
Enclosure/Fence 9/22/2023 Corrections Issued MICHAEL PELHAM
Enclosure/Fence 9/29/2023 Approved EVAN COOPER
Final 10/12/2023 Corrections Issued EVAN COOPER
Pool Equipment Noise Test 10/12/2023 Approved JAMES VORHIS
SGSOV-Seismic Gas S/O Valve 10/12/2023 SGSOV Approved EVAN COOPER
Final 12/21/2023 Conditional Approval EVAN COOPER
Special/Order Compliance 12/22/2023 Approved EVAN COOPER