18038 W BLUE SAIL DR 90272
Certificate Information: 18038 W BLUE SAIL DR 90272
- Application / Permit
- 21047-20000-02669
- Plan Check / Job No.
- B21VN16974
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) POOL W/ TANNING SHELF (IRR 41' X 18'-5") & SPA (10' X 13'- 3/4") ON PILES PER ENG'R DESIGN
- Permit Issued
- Issued on 8/11/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2022 | NILOOFAR MEHRAIN |
| Corrections Issued | 1/18/2022 | NILOOFAR MEHRAIN |
| Quality Review Completed | 1/21/2022 | STEVEN KIM |
| Building Plans Picked Up | 1/25/2022 | APPLICANT |
| Applicant returned to address corrections | 6/21/2022 | NILOOFAR MEHRAIN |
| Plan Check Approved | 7/13/2022 | NILOOFAR MEHRAIN |
| Issued | 8/11/2022 | APPLICANT |
| CofO in Progress | 12/22/2023 | EVAN COOPER |
| Permit Finaled | 1/2/2024 | DANIEL ORRANTE |
| CofO Issued | 1/2/2024 | DANIEL ORRANTE |
| Permit Finaled | 1/2/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Coastal Zone | Cleared | 5/31/2022 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 5/31/2022 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 5/31/2022 | MIGUEL GAMBOA |
| ZI | Cleared | 5/31/2022 | MIGUEL GAMBOA |
| Grading Pre-Inspection | Cleared | 6/21/2022 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Resto Group The; Lic. No.: 898290-B | 311 N ROBERTSON SUITE 732 BEVERLY HILLS, CA 90211 |
| Engineer | Kessler,, Dale Edward; Lic. No.: C58524 | 16043 HART ST VAN NUYS, CA 91406 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/15/2022 | Approved | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 9/27/2022 | Partial Approval | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 11/4/2022 | Partial Approval | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 12/13/2022 | Corrections Issued | BRENDAN LOONEY |
| Pre-Gunite | 12/13/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 12/19/2022 | Approved | MICHAEL PELHAM |
| Grounding or Bonding | 12/19/2022 | Partial Approval | MICHAEL PELHAM |
| Pool Piping | 12/19/2022 | Partial Approval | MICHAEL PELHAM |
| Pre-Gunite | 12/19/2022 | Approved | MICHAEL PELHAM |
| Gas Piping or Gas Test | 1/24/2023 | Approved | MICHAEL PELHAM |
| Rough-Electrical | 1/24/2023 | Approved | MICHAEL PELHAM |
| Rough-Plumbing | 1/24/2023 | Approved | MICHAEL PELHAM |
| Deputy Shotcrete | 5/17/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Gas Piping or Gas Test | 5/31/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Rough-Electrical | 5/31/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Rough-Plumbing | 5/31/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Pool Equipment Noise Test | 6/7/2023 | Not Ready for Inspection | JAMES VORHIS |
| Pool Piping | 6/8/2023 | Approved | KENNETH NAGLE |
| Enclosure/Fence | 9/15/2023 | Corrections Issued | KENNETH NAGLE |
| Enclosure/Fence | 9/22/2023 | Corrections Issued | MICHAEL PELHAM |
| Enclosure/Fence | 9/29/2023 | Approved | EVAN COOPER |
| Final | 10/12/2023 | Corrections Issued | EVAN COOPER |
| Pool Equipment Noise Test | 10/12/2023 | Approved | JAMES VORHIS |
| SGSOV-Seismic Gas S/O Valve | 10/12/2023 | SGSOV Approved | EVAN COOPER |
| Final | 12/21/2023 | Conditional Approval | EVAN COOPER |
| Special/Order Compliance | 12/22/2023 | Approved | EVAN COOPER |