4315 E SAN RAFAEL AVE 90065
Certificate Information: 4315 E SAN RAFAEL AVE 90065
- Application / Permit
- 21047-20000-02655
- Plan Check / Job No.
- B21VN16866
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) PREFAB SPA (18' X 8') ON PILES PER ENG'R DESIGN
- Permit Issued
- Issued on 7/5/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2022 | NILOOFAR MEHRAIN |
| Corrections Issued | 1/18/2022 | NILOOFAR MEHRAIN |
| Quality Review Completed | 1/21/2022 | STEVEN KIM |
| Building Plans Picked Up | 1/24/2022 | APPLICANT |
| Applicant returned to address corrections | 4/28/2022 | NILOOFAR MEHRAIN |
| Plan Check Approved | 6/15/2022 | NILOOFAR MEHRAIN |
| Issued | 7/5/2022 | APPLICANT |
| CofO in Progress | 9/11/2023 | OSVALDO PARAMO |
| CofO Issued | 9/12/2023 | RONALD MYRICK |
| Permit Finaled | 9/12/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Specific Plan | Cleared | 3/31/2022 | NASHYA JENSEN |
| ZI | Cleared | 3/31/2022 | NASHYA JENSEN |
| Grading Pre-Inspection | Cleared | 6/15/2022 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | Alpha Structural Inc; Lic. No.: 663409-B | 8334 FOOTHILL BLVD SUNLAND, CA 91040 |
| Engineer | Demers,, Joe Alan; Lic. No.: C71535 | 894 SANTA MARIA CIRCLE DUARTE, CA 91010 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/11/2022 | Partial Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 10/20/2022 | Off-Hour Fees Due | |
| Excavation/Setback/Form/Re-Bar | 10/20/2022 | Partial Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 11/16/2022 | Approved | OSVALDO PARAMO |
| Final | 4/11/2023 | Corrections Issued | OSVALDO PARAMO |
| Pre-Gunite | 4/11/2023 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 4/11/2023 | SGSOV Approved | OSVALDO PARAMO |
| Final | 5/10/2023 | Corrections Issued | OSVALDO PARAMO |
| Final | 5/25/2023 | Corrections Issued | OSVALDO PARAMO |
| Final | 6/12/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 7/5/2023 | Conditional Approval | OSVALDO PARAMO |