4339 N LAURELGROVE AVE 91604
Certificate Information: 4339 N LAURELGROVE AVE 91604
- Application / Permit
- 21047-20000-02638
- Plan Check / Job No.
- B21VN16722
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 17' X 32' POOL W/ 7' X 7' SPA INSIDE PER STANDARD PLAN #268
- Permit Issued
- Issued on 5/11/2022
- Issuing Office
- Current Status
- CofO Issued on 11/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/15/2021 | RAPHAEL ROSAS |
| Corrections Issued | 12/16/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 3/10/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 4/8/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 5/2/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 5/4/2022 | APPLICANT |
| Issued | 5/11/2022 | APPLICANT |
| CofO in Progress | 11/14/2022 | CHRISTOPHE COCHRAN |
| CofO Issued | 11/19/2022 | MICHAEL SMITH |
| Permit Finaled | 11/19/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/25/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Ahern Construction Corporation; Lic. No.: 687780-B | 3835-R THOUSAND OAKS BLVD #118 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/31/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Gas Piping or Gas Test | 6/13/2022 | Approved | ARAM AVEDISIAN |
| Pre-Gunite | 6/13/2022 | Corrections Issued | ARAM AVEDISIAN |
| Pre-Gunite | 7/6/2022 | Approved | CHRISTOPHE COCHRAN |
| Deputy Shotcrete | 7/7/2022 | Conditional Approval | CHRISTOPHE COCHRAN |
| Rough-Electrical | 8/22/2022 | Approved | CHRISTOPHE COCHRAN |
| Rough-Plumbing | 8/22/2022 | Approved | CHRISTOPHE COCHRAN |
| Grounding or Bonding | 9/20/2022 | Approved | CHRISTOPHE COCHRAN |
| Enclosure/Fence | 10/25/2022 | Approved | CHRISTOPHE COCHRAN |
| Pool Equipment Noise Test | 11/2/2022 | Approved | ALFREDO FLORES |
| Excavation/Setback/Form/Re-Bar | 11/14/2022 | Approved | CHRISTOPHE COCHRAN |
| Final | 11/14/2022 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 11/14/2022 | SGSOV Approved | CHRISTOPHE COCHRAN |