228 S HUDSON AVE 90004
Certificate Information: 228 S HUDSON AVE 90004
- Application / Permit
- 21047-20000-02637
- Plan Check / Job No.
- B21VN16713
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) POOL (34' X 16') & SPA (9' X 9') PER ENG'R DESIGN
- Permit Issued
- Issued on 3/17/2022
- Issuing Office
- Current Status
- CofO Issued on 12/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2022 | NILOOFAR MEHRAIN |
| Corrections Issued | 1/11/2022 | NILOOFAR MEHRAIN |
| Quality Review Completed | 1/19/2022 | STEVEN KIM |
| Building Plans Picked Up | 1/19/2022 | APPLICANT |
| Applicant returned to address corrections | 1/21/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 3/15/2022 | NILOOFAR MEHRAIN |
| Plan Check Approved | 3/15/2022 | NILOOFAR MEHRAIN |
| Issued | 3/17/2022 | APPLICANT |
| CofO in Progress | 11/21/2022 | JOSEPH MCGARRY |
| Permit Finaled | 12/10/2022 | DEROLD HAUFF |
| CofO Issued | 12/10/2022 | DEROLD HAUFF |
| Permit Finaled | 12/10/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 2/14/2022 | MIGUEL GAMBOA |
| HPOZ | Cleared | 2/14/2022 | MIGUEL GAMBOA |
| ZI | Cleared | 2/14/2022 | MIGUEL GAMBOA |
Contact Information
| Contractor | Terra Home Remodeling Inc; Lic. No.: 1014316-B | 17216 SATICOY ST #221 VAN NUYS, CA 914062103 |
| Engineer | Hajdari,, Genti; Lic. No.: C88031 | 140 S MENTOR AVE APT #207 PASADENA, CA 91106 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 4/19/2022 | Corrections Issued | STUART CHAPMAN |
| Pre-Gunite | 4/29/2022 | Approved | ARTHUR SARGSYAN |
| Deputy Shotcrete | 5/11/2022 | Approved | ARTHUR SARGSYAN |
| Gas Piping or Gas Test | 7/1/2022 | Approved | ADAM ESCOTO |
| Grounding or Bonding | 7/13/2022 | Approved | ADAM ESCOTO |
| Enclosure/Fence | 10/4/2022 | Corrections Issued | JOSEPH MCGARRY |
| Enclosure/Fence | 10/6/2022 | Corrections Issued | MICHAEL LEWIS |
| Equipment Noise Level | 10/6/2022 | Not Ready for Inspection | ZEYDI STEWART |
| Enclosure/Fence | 11/9/2022 | Approved | MICHAEL LEWIS |
| Equipment Noise Level | 11/15/2022 | Approved | ZEYDI STEWART |
| Excavation/Setback/Form/Re-Bar | 11/16/2022 | Approved | JOSEPH MCGARRY |
| Final | 11/16/2022 | OK to Issue CofO | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 11/16/2022 | SGSOV Approved | JOSEPH MCGARRY |