4452 N ETHEL AVE 91604

Certificate Information: 4452 N ETHEL AVE 91604

Application / Permit
21047-20000-02635
Plan Check / Job No.
B21VN16703
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
*EPLAN* (N) POOL (OUTSIDE DIM. 25' X 16') AND SPA (INSIDE DIM. 6' X 6') PER STD PLAN #268
Permit Issued
Issued on 3/27/2022
Issuing Office
Current Status
CofO Issued on 4/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2021 APPLICANT
Assigned to Plan Check Engineer 12/21/2021 VIVIAN LAO
Corrections Issued 12/21/2021 VIVIAN LAO
Plan Check Approved 3/18/2022 VIVIAN LAO
Issued 3/27/2022 APPLICANT
CofO in Progress 4/10/2023 CHRISTOPHE COCHRAN
Permit Finaled 4/18/2023 MICHAEL SMITH
CofO Issued 4/18/2023 MICHAEL SMITH
Permit Finaled 4/18/2023 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 3/15/2022 TINA MIRANDA
Construction within easement Cleared 3/15/2022 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 9/21/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Gas Piping or Gas Test 9/22/2022 Approved CHRISTOPHE COCHRAN
Pre-Gunite 9/22/2022 Approved CHRISTOPHE COCHRAN
Deputy Shotcrete 9/28/2022 Conditional Approval CHRISTOPHE COCHRAN
Deck 11/22/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Deck 11/28/2022 Corrections Issued CHRISTOPHE COCHRAN
Deck 12/7/2022 Approved MICHEL ABAJAN
Enclosure/Fence 3/7/2023 Corrections Issued CHRISTOPHE COCHRAN
Enclosure/Fence 3/22/2023 Approved CHRISTOPHE COCHRAN
Enclosure/Fence 3/28/2023 Approved CHRISTOPHE COCHRAN
Pool Equipment Noise Test 3/31/2023 Approved FELIPE PENICHE
Excavation/Setback/Form/Re-Bar 4/3/2023 Approved JOHN COLEMAN
Final 4/3/2023 Corrections Issued JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 4/3/2023 SGSOV Approved JOHN COLEMAN
Final 4/10/2023 OK to Issue CofO CHRISTOPHE COCHRAN