7050 S ARIZONA AVE 90045

Certificate Information: 7050 S ARIZONA AVE 90045

Application / Permit
21047-20000-02609
Plan Check / Job No.
B21VN16538
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 17' X 40' POOL WITH A 9' X 9' SPA PER LA CITY STANDARD PLAN # 265 AND AUTO POOL COVER.
Permit Issued
Issued on 1/9/2022
Issuing Office
Current Status
CofO Issued on 10/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/1/2021 APPLICANT
Assigned to Plan Check Engineer 12/2/2021 PARISA ZAHABI
Corrections Issued 12/2/2021 PARISA ZAHABI
Issued 1/9/2022 APPLICANT
Building Plans Picked Up 1/13/2022 APPLICANT
CofO in Progress 10/19/2022 HERBERT GIRON
Permit Finaled 10/24/2022 DANIEL ORRANTE
CofO Issued 10/24/2022 DANIEL ORRANTE
Permit Finaled 10/24/2022 DANIEL ORRANTE

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Avanti Pools Inc; Lic. No.: 772516-C53 8138 ORION AVE      VAN NUYS, CA 91406
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/10/2022 Approved BOBBY KEY
Grounding or Bonding 2/10/2022 Approved BOBBY KEY
Pool Piping 2/10/2022 Approved BOBBY KEY
Pre-Gunite 2/10/2022 Approved BOBBY KEY
Gas Piping or Gas Test 2/11/2022 No Access for Inspection CLAYTON GRAHAM
Rough-Electrical 2/11/2022 No Access for Inspection CLAYTON GRAHAM
Gas Piping or Gas Test 2/15/2022 Approved DEANDRE HOFFMAN
Rough-Electrical 2/15/2022 Approved DEANDRE HOFFMAN
Deputy Shotcrete 2/18/2022 Conditional Approval BOBBY KEY
Deputy Shotcrete 2/24/2022 Conditional Approval BOBBY KEY
Enclosure/Fence 4/25/2022 Corrections Issued JESUS RODRIGUEZ
Enclosure/Fence 5/16/2022 Conditional Approval JESUS RODRIGUEZ
Deck 6/28/2022 Approved JESUS RODRIGUEZ
Enclosure/Fence 6/30/2022 Approved BOBBY KEY
Final 8/2/2022 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 8/2/2022 SGSOV Not Ready HERBERT GIRON
Final 8/8/2022 Partial Approval HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 8/8/2022 SGSOV Approved HERBERT GIRON
Final 8/10/2022 Corrections Issued HERBERT GIRON
Final 10/18/2022 OK to Issue CofO HERBERT GIRON