101 N GROVERTON PL 90077
Certificate Information: 101 N GROVERTON PL 90077
- Application / Permit
- 21047-20000-02571
- Plan Check / Job No.
- B21VN16187
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- REMODEL THE (E) POOL. ADD A 8 X 8 SPA 3.5 FT. DEEP. AND A BAJA SHELF 18 DEEP WITH NEW EQUIPT. ALL WORK INSIDE THE (E) SHELL. WORK PER ENGINEERING.
- Permit Issued
- Issued on 12/9/2021
- Issuing Office
- Current Status
- CofO Issued on 8/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2021 | PETER MOSESIAN |
| Plan Check Approved | 11/29/2021 | COLIN LOREDO |
| Building Plans Picked Up | 12/2/2021 | APPLICANT |
| Issued | 12/9/2021 | APPLICANT |
| CofO in Progress | 7/15/2022 | CHRISTOPHER WILSON |
| CofO in Progress | 7/15/2022 | CHRISTOPHER WILSON |
| Permit Finaled | 8/1/2022 | DANIEL ORRANTE |
| CofO Issued | 8/1/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/1/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Avanti Pools Inc; Lic. No.: 772516-C53 | 8138 ORION AVE VAN NUYS, CA 91406 |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/21/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Grounding or Bonding | 1/21/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Pool Piping | 1/21/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Rough-Electrical | 1/21/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Grounding or Bonding | 1/24/2022 | Partial Approval | CHRISTOPHER WILSON |
| Pool Piping | 1/24/2022 | Approved | CHRISTOPHER WILSON |
| Pre-Gunite | 1/24/2022 | Approved | CHRISTOPHER WILSON |
| Rough-Electrical | 1/24/2022 | Partial Approval | CHRISTOPHER WILSON |
| Rough-Plumbing | 1/24/2022 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Shotcrete | 1/26/2022 | Conditional Approval | MICHAEL PELHAM |
| Gas Piping or Gas Test | 3/23/2022 | Approved | MICHAEL PELHAM |
| Grounding or Bonding | 3/23/2022 | Partial Approval | MICHAEL PELHAM |
| Enclosure/Fence | 5/12/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Enclosure/Fence | 5/18/2022 | Approved | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 7/5/2022 | SGSOV Not Ready | CHRISTOPHER WILSON |
| Final | 7/12/2022 | OK to Issue CofO | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 7/12/2022 | SGSOV Approved | CHRISTOPHER WILSON |